POWERGRID won 24 TBCB projects in financial year 2024-25, with project costs of about INR 92,000 crores, a 57.34% market share in terms of NCT cost and about 54.55% in terms of project wins. POWERGRID is targeting to commission the Dausa substation in less than 9 months from Sikar, and expects it to be commissioned in 1 month or 2 months. POWERGRID has 1,533 transmission lines, 180,239 circuit kilometers, more than 2.9 lakh towers, 283 substations and 564,961 MVA capacity. POWERGRID maintained system availability at 99.82% in financial year 2024-2025. POWERGRID maintained a minimum return on equity level of more than 12% or 13% for TBCB projects and said it was winning projects while maintaining that level.

The numbers management gave

Results

  • POWERGRID maintained system availability at 99.82% in financial year 2024-2025.
    Show source
    We have been maintaining our system availability at 99.82% in financial year 2024-2025.
  • POWERGRID's capitalization increased from INR 7,618 crores to INR 9,014 crores in financial year 2024-25.
    Show source
    In capitalization also, we have increased from INR 7,618 crores to INR 9,014 crores.
  • POWERGRID achieved 99.82% operational performance, above the 99.75% level at which it normally receives incentive, which is capped at that value, in financial year 2024-25.
    Show source
    In Operational side, as I said that we achieved 99.82%, which is more than 99.75% at which we are normally getting incentive because after 99.75%, normally, incentive is capped at that particular value.
  • POWERGRID recorded 0.27 tripping per line per year in financial year 2024-25, indicating that one transmission line trips in almost four years.
    Show source
    And last year also, we have 0.27 tripping per line per year, which indicate that our one transmission line trips in almost 4 years.
  • POWERGRID's standalone revenue or income was INR 12,482 crores and PAT was INR 4,336 crores in quarter 4 of financial year 2024-25.
    Show source
    Next, in financial performance, standalone in quarter 4, we have revenue or income of INR 12,482 crores, PAT at INR 4,336 crores.
  • POWERGRID's consolidated income was INR 12,591 crores and PAT was INR 4,143 crores in quarter 4 of financial year 2024-25.
    Show source
    In consolidated basis, we have INR 12,591 crores and PAT at INR 4,143 crores.
Show 27 more statements

Results

  • POWERGRID's total income was INR 46,325 crores and profit was INR 15,354 crores in financial year 2024-25.
    Show source
    In case of financial performance for 2024-25, our total income is INR 46,325 crores with profit of INR 15,354 crores.
  • POWERGRID's consolidated income was INR 47,459 crores against INR 46,913 crores last year, and PAT was INR 15,521 crore in financial year 2024-25.
    Show source
    On a consolidated basis, our income is INR 47,459 crores against INR 46,913 crores last year and PAT also INR 15,521 crore in financial year 24-25.
  • POWERGRID had about INR 290,715 crores as Gross Fixed Assets in financial year 2024-25.
    Show source
    In financial performance, we have about INR 290,715 crores as Gross Fixed Assets.
  • POWERGRID had about INR 36,341 crores of capital work in progress in financial year 2024-25.
    Show source
    Capital work in progress is about INR 36,341 crores.
  • POWERGRID's net worth increased from INR 87,145 crore to INR 92,663 crore in financial year 2024-25.
    Show source
    Net worth has increased from INR 87,145 crore to INR 92,663 crore.
  • POWERGRID's earnings per share was INR 16.69 in financial year 2024-25.
    Show source
    Our earnings per share is at INR 16.69.
  • POWERGRID's book value per share was INR 99.63 in financial year 2024-25.
    Show source
    Book value per share is INR 99.63.
  • POWERGRID's debt-to-equity ratio was 59:41 and return on net worth was 16.75% in financial year 2024-25.
    Show source
    Debt-to-equity ratio is 59:41 and return on net worth is 16.75%.
  • POWERGRID's Telecom segment crossed INR 1,000 crores of income for the first time and achieved INR 1,128 crores, against INR 910 crores in last financial year.
    Show source
    We have achieved INR 1,128 crores as against INR 910 crores in last financial year.
  • POWERGRID's Telecom segment added 75 new customers in financial year 2024-25.
    Show source
    New customers added 75 numbers.
  • POWERGRID's Telecom segment had 100% backbone availability in financial year 2024-25.
    Show source
    Our backbone availability is again 100%, and major projects under implementation is Data Center at Manesar, and then Zone II Data Center at Chennai then Government projects, ERNET and NKN National Knowledge Network.
  • POWERGRID's Consultancy segment revenue from operations was INR 799 crores against INR 553 crores in last financial year.
    Show source
    Next, in Consultancy segment, we have revenue from operations of INR 799 crores against INR 553 crores in last financial year.
  • POWERGRID's billing was INR 36,877 crores, realization was INR 38,284 crores, and realization was 103.8% of billing in financial year 2024-25.
    Show source
    Next, in Commercial, we have a billing of INR 36,877 crores with realization of INR 38,284 crores, realization at 103.8%.
  • POWERGRID reduced its dividend payout to fund future needs; last year it had INR 15,500 crores, while this year profit is again in the same range and Net Worth increased from INR 87,000 crore to about more than INR 90,000 crores, explaining the ROE impact.
    Show source
    And this year, also, our profit is again in the same range, but our Net Worth has increased from INR 87,000 crore to about more than INR 90,000 crores.

Money and capital

  • POWERGRID's Government of India shareholding was 51.34%, FII shareholding was 26.78% and domestic institutional investors' shareholding was 18.35%.
    Show source
    Today, we have Government of India shareholding as 51.34%, FII 26.78% and domestic institutional investors as 18.35%.
  • POWERGRID's share price was Rupees 366 per share and its market cap was INR 3.4 trillion in September’24, when it achieved its highest market cap.
    Show source
    POWERGRID has achieved highest market cap in September’24 where price of POWERGRID share was Rupees 366 per share with market cap of INR 3.4 trillion.
  • POWERGRID achieved INR 26,255 crores of Capex in financial year 2024-25, surpassing its Capex target of about INR 20,000 crores.
    Show source
    So, we achieved INR 26,255 crores Capex in financial year 2024-25.
  • POWERGRID had debt of INR 130,965 crores in financial year 2024-25.
    Show source
    We have debt of INR 130,965 crores.
  • POWERGRID's market capitalization was about 2.4x its market capitalization in financial year 2021.
    Show source
    Then in terms of Investor-centric growth, we have this increase of market cap, about 2.4x what we had in financial year 2021.
  • POWERGRID's share price CAGR from FY 21-25 was 24.4%.
    Show source
    Price CAGR from FY 21-25 is 24.4%.
  • POWERGRID paid a dividend of INR 10.5 per share during financial year 2024-25 on cash basis.
    Show source
    Dividend paid during financial year on cash basis is INR 10.5 per share.
  • POWERGRID's market capitalization was INR 270,136 crores and its share price was INR 290.35 per share at the end of financial year 2025.
    Show source
    So, at the end of financial year 2025, it was INR 270,136 crores with the share price of INR 290.35 per share.
  • POWERGRID's investment or capex had a 5-year CAGR of about 23.5%.
    Show source
    Investment or capex, we have this 5-year CAGR, about 23.5%.
  • POWERGRID had capex of INR 68,000 crore in projects from financial year '21 to '25.
    Show source
    And from financial year '21 to '25 INR 68,000 crore projects we have had capex in various areas.
  • POWERGRID's dividend payout has been reduced by about INR 2 – INR 2.25 because it requires equity for project execution; the dividend may change from INR 9 next year and can further reduce depending on expected capex of about INR 28,000 crores to INR 30,000 crores.
    Show source
    So that is why our dividend payout is reduced by about INR 2 – INR 2.25.
  • The company has about INR 1,54,000 crore of projects in hand and expects capex of about INR 28,000 crores in FY 2025-26, INR 35,000 crores in '26-'27, and INR 45,000 crore in '27-'28, totaling about INR 108,000 crores or INR 110,000 crores; most HVDC capex for Kaithal to Pang and Khavda to Nagpur will be after 2 years, with about 20% or 30% incurred up to 2027-'28.
    Show source
    We have mentioned that we have about INR 1,54,000 crore projects in hand, and say, about INR 28,000 crores in FY 2025-26 and INR 35,000 crores in '26-'27 and '27-'28, INR 45,000 crore, which adds up to, say, about INR 108,000 crores or INR 110,000 crores.
  • The company will claim the increased IDC amount resulting from project delays and overruns.
    Show source
    So, we will claim that amount also.

What it expects ahead

What management expects

  • POWERGRID is targeting to commission the Dausa substation in less than 9 months from Sikar, and expects it to be commissioned in 1 month or 2 months.
    Show source
    One more substation, which we are targeting to better our performance from Sikar to Dausa, we are expecting, we are trying to commission even less than 9 months, which is expected to be commissioned may be in 1 month or 2 months, but we are excelling in project management.
  • POWERGRID expects to deploy these technologies in financial year 25-26.
    Show source
    So, these technologies, we are expecting to deploy in financial year 25-26.
  • POWERGRID is targeting capex of INR 28,000 crores in financial year '25-'26, INR 35,000 crores in financial year '26-'27 and INR 45,000 crores in financial year '27-'28; the INR 28,000 crores target may increase to more than INR 30,000 crores as visibility develops.
    Show source
    Capex outlook, we are targeting INR 28,000 crores in financial year '25-'26.
  • POWERGRID is expecting capitalization of about INR 23,000 crores to INR 25,000 crores in financial year 2025-26.
    Show source
    In financial year 2025-26, we are expecting about INR 23,000 crores to INR 25,000 crores capitalization.
  • POWERGRID expects visibility of more projects in its pipeline to emerge after maybe 2, 3 months.
    Show source
    Tyagi: This is as of now, but more projects are in pipeline, visibility of those projects will be seen after maybe 2, 3 months.
  • The Government of India's National Electricity Plan for transmission envisaged about INR 10 lakh crore of spending on transmission system development; POWERGRID said it saw no challenge or issue in achieving the target.
    Show source
    Tyagi: As we have indicated that a $10 trillion economy by 2032 and in transmission itself as per NEP issued by Government of India, National Electricity Plan for transmission, about INR 10 lakh crore are to be spent in transmission system development.
Show 14 more statements

What management expects

  • POWERGRID said there was no clear visibility on the project until the Government of India issued a clear methodology, which it would then consider; it expected some clarity from the Government of India in quarter 2.
    Show source
    So as of now, there is no clear visibility.
  • The NEP indicates intra-state capex of about INR 3 lakh crore plus, which management said would be very difficult for the states to achieve without TBCB execution; Uttar Pradesh, Madhya Pradesh, Rajasthan, Odisha, and Maharashtra have issued intra-state TBCB projects, and Power Grid Corporation of India Limited expects to win some intra-state transmission projects.
    Show source
    Tyagi: No. Intra-state, as per NEP, they have shown that they have indicated that there will be expenditure or capex of about INR 3 lakh crore plus in intra-state.

Orders

  • POWERGRID won 24 TBCB projects in financial year 2024-25, with project costs of about INR 92,000 crores, a 57.34% market share in terms of NCT cost and about 54.55% in terms of project wins.
    Show source
    Next, In financial year 2024-25, we have won 24 numbers of TBCB projects, where cost of projects is about INR 92,000 crores and market share 57.34% in terms of NCT cost and about 54.55% in terms of project wins.
  • POWERGRID won the transmission system for evacuation of power from Rajasthan Phase IV, Part 4, Part A, in the Bikaner area to evacuate power from Rajasthan to various parts of Northern states.
    Show source
    The major projects, which we have won is transmission system for evacuation of power from Rajasthan Phase IV, Part 4, Part A. It is in Bikaner area, power generated in RE area in Bikaner to Siwani, then to Haryana, Punjab and Delhi.
  • POWERGRID won its first TBCB HVDC project from Khavda to Nagpur, with about 6,000 MW capacity, to transmit power from Khavda to Nagpur and then to Maharashtra and other parts of the country.
    Show source
    Then we have a very important and first TBCB HVDC project won by POWERGRID from Khavda to Nagpur, which is about 6,000 MW capacity.
  • POWERGRID won the transmission system for Kurnool area Phase I, for about 4.5 GW.
    Show source
    So, transmission system for Kurnool area Phase I, which is for about 4.5 GW.
  • POWERGRID won a project in Khavda area, Phase IV, Part B, for 7 GW.
    Show source
    One more project, which we have won in Khavda area, Phase IV, which is Part B and for 7 GW.
  • POWERGRID's Telecom segment received total orders of INR 412 crores in financial year 2024-25.
    Show source
    Total order received INR 412 crores.
  • POWERGRID had 16 ongoing international assignments and 8 orders during financial year 2025.
    Show source
    In International, we have 16 ongoing assignments and 8 orders during financial year 2025.
  • POWERGRID had 80 ongoing domestic assignments and 55 new orders during financial year 2025.
    Show source
    In Domestic, we have 80 ongoing assignments and 55 new orders during financial year 2025.
  • POWERGRID has about INR 1,54,680 crores of works in hand, comprising about INR 105,000 crores in TBCB, about INR 37,000 crores in new RTM, 9,580 crore in ongoing RTM and INR 2,785 crores in others.
    Show source
    Today, we have about INR 1,54,680 crores works in hand, in TBCB about INR 105,000 crores, new RTM about INR 37,000 crores, ongoing RTM 9,580 crore and others INR 2,785 crores.
  • POWERGRID's project pipeline is about INR 45,000 crore to INR 46,000 crore, including about INR 34,000 crore of projects under bidding and INR 10,000 crore to INR 11,000 crore of projects yet to be bid.
    Show source
    Tyagi: Yes, it is a pipeline, the projects which are already in pipeline is about INR 45,000 crore to INR 46,000 crore, out of which about INR 34,000 crore projects are already under bidding and INR 10,000 crore to INR 11,000 crore projects are yet to be bid.
  • POWERGRID's INR 92,000 crores of projects in FY '25 represents its internal cost at which it awarded the projects, not NCT cost.
    Show source
    It is our internal cost, at which we have awarded the projects.
  • POWERGRID won INR 92,000 crore of projects in a single year.
    Show source
    As you can also appreciate INR 92,000 crore projects in a single year is not a small thing.

What it is building and selling

Projects and capacity

  • POWERGRID has 1,533 transmission lines, 180,239 circuit kilometers, more than 2.9 lakh towers, 283 substations and 564,961 MVA capacity.
    Show source
    We operate in almost all the states and all the districts of the country, and we are playing a very important role in meeting the power demand of the country with transmission lines of 1,533 numbers with 180,239 circuit Page 3 of 24 Power Grid Corporation of India Limited kilometers and more than 2.9 lakh towers spread across width and breadth of the country with 283 substations and 564,961 MVA capacity.
  • POWERGRID had 66 Gas Insulated Substations.
    Show source
    So as on today, we have 66 numbers of Gas Insulated Substations.
  • POWERGRID had more than 3,800 Transformers and Reactors.
    Show source
    We have more than 3,800 Transformers and Reactors.
  • POWERGRID commissioned at Navsari the first digital substation in the world at 765 kV level, for evacuation of power from Khavda area in Gujarat to Maharashtra.
    Show source
    Next, we have commissioned one of the largest digital substations at 765 kV.
  • POWERGRID is using cranes for tower erection at 400 kV and 765 kV levels, and drone-based stringing for power-line and important crossings and in hilly areas.
    Show source
    We have also introduced advanced tower erection techniques like we are using cranes for tower erection at 400 kV and 765 kV level.
  • POWERGRID erected a 765 kV DA type tower weighing about 37.4 metric tons in a single day in the Banaskantha to Ahmedabad line.
    Show source
    So, 765 kV DA type tower having weight of about 37.4 metric tons was erected in a single day in Banaskantha to Ahmedabad line.
Show 35 more statements

Projects and capacity

  • POWERGRID commissioned five stations in financial year 2025: 765/400 kV Sikar-II, 765/400/220 kV Kurnool-II in Andhra Pradesh, 765/400 kV Navsari, 400/220 kV Navi Mumbai, and Khavda Pooling Station–KPS-II in Gujarat.
    Show source
    These 5 stations have been commissioned in financial year 2025.
  • POWERGRID commissioned 765 kV transmission lines from Fatehgarh-II to Bhadla-II, Bhadla-II to Sikar II, Sikar II to Aligarh, and Kurnool III to Kurnool new.
    Show source
    Important transmission lines, 765 kV from Fatehgarh-II to Bhadla-II, then Bhadla-II to Sikar II and 765 kV Sikar II to Aligarh, then 765 kV Kurnool III to Kurnool new.
  • POWERGRID commissioned 400 kV transmission lines from Navsari to Magarwada, Sikar II to Neemrana, Jamnagar to Jam Khambaliya, Raipur to Dhamtari, and Banaskantha to Sankhari.
    Show source
    In 400 kV, from Navsari to Magarwada, Sikar II to Neemrana, Jamnagar to Jam Khambaliya, Raipur to Dhamtari, Banaskantha to Sankhari.
  • POWERGRID developed a substation inspection robot in association with IIT Kanpur and has used it at its 400 kV substations.
    Show source
    One robot has been developed in association with IIT Kanpur, and which has been used at our 400 kV substations.
  • POWERGRID is deploying its substation inspection robot at the 765 kV/400 kV Jhatikara substation, which is close to Delhi.
    Show source
    Now we are deploying this robot at our 765 kV/400 kV Jhatikara substation, which is close to Delhi.
  • POWERGRID has taken up a pilot project for SF6 circuit breakers at 145 kV level and is considering 220 kV and 400 kV.
    Show source
    Next, further in Technology development, we are working for SF6 circuit breakers at 145 kV level, already pilot project is already taken up.
  • POWERGRID expects its mobile GIS Bay for 400 kV, 132 kV and 220 kV to restore power supply in about 6 to 8 hours if a bay is damaged by a natural calamity such as an earthquake or cyclone.
    Show source
    So, this mobile GIS Bay will help in case of any natural calamity or any, suppose, earthquake or cyclone is there and a particular bay is damaged, So power supply can be restored at very fast that it can be maybe 6 to 8 hours, we can restore the power supply by using mobile GIS bays.
  • POWERGRID expects its insulated cross arm at 400 kV to reduce RoW from 46 meters to about 36 meters; two parties are already developed and the insulated cross arm is expected to supply in May end.
    Show source
    This one is expected to supply in May end, which will reduce the RoW from, say, 46 meters to about 36 meters.
  • POWERGRID is laying a 12-kilometer underground cable between Minamarg and Zojila top at Zojila pass in J&K to bypass the overhead line, which can be damaged by avalanches, and maintain power supply to Leh.
    Show source
    Next, one more initiative we are taking, especially in J&K, in Zojila pass, where 12-kilometer underground cable is being laid between Minamarg and Zojila top to bypass the over headline because whenever any avalanche is there, so that leads to damage of transmission line towers.
  • POWERGRID has commissioned an 85-megawatt Solar PV power project at Nagda in April 2025, which has started generating power, and sells about 70% to 80% of its electricity in GDAM (Green Day Ahead Market) and real time markets in power exchange.
    Show source
    We have commissioned 85-megawatt Solar PV power project at Nagda which was commissioned in April 2025, which has already started generating power and we are selling electricity about 70% to 80% in GDAM (Green Day Ahead Market) and real time markets in power exchange.
  • POWERGRID is likely to commission a 400 kV/220 kV, 315 MVA ICT in financial year '25-'26.
    Show source
    And one more transformer, which is likely to be commissioned in financial year '25-'26 is 400 kV/220 kV, 315 MVA ICT, which is likely to be commissioned in financial year '25-'26.
  • POWERGRID's Neemrana Green Hydrogen pilot will generate RE power from solar to produce green hydrogen, which will be converted to electricity at night for captive use at Neemrana; the project cost is about INR 32 crores, it is likely to be awarded in June 2025 and has an implementation schedule of about 12 months.
    Show source
    The project cost is about INR 32 crores, and this is likely to be awarded in June 2025 with the implementation schedule of about 12 months.
  • POWERGRID said ROW compensation policies issued by the Government of India and their adoption by State Government caused delays in some projects in 2024-25, and expected execution to be much faster in 2025-26 because guidelines were in place.
    Show source
    So, in 2024-25, there has been delays in some projects.
  • POWERGRID expected to award the HVDC Leh-Ladakh project in quarter 2 and said it did not expect further delay after quarter 2.
    Show source
    And in quarter 2, it is likely to be awarded.
  • For the Khavda to Nagpur HVDC project, the NCT cost is about INR 24,000 crores, while the actual cost may be INR 33,000 to INR 34,000 crores; other projects are within 5% of the NCT value.
    Show source
    But in this particular case, cost -- NCT cost is about INR 24,000 crores, but actual cost may be INR 33,000, INR 34,000 crores.
  • The South Olpad project RFP has been issued, bids are likely to be submitted very soon, and the tender is expected to be finalized very soon; the bid submission date of 16th May was extended because prospective bidders had queries.
    Show source
    So, there was a date of 16th May, which has been increased now because of some, they've got some queries from the prospective bidders.
  • Initial estimates put the Paradeep–Andaman–Singapore link project at INR 30,000-plus crore.
    Show source
    Tyagi: As per initial estimates, I cannot say exactly, but it will be INR 30,000-plus crore.
  • The Singapore to India link may have a capacity of about 2,000 MW, while the Andaman to Paradeep link may have a capacity of about 250 MW.
    Show source
    Tyagi: Capacity, if it is, say, between Singapore to India, it may be about 2,000 MW.
  • Under the NEP pipeline, more than INR 9 lakh crore of projects are to be completed by 2032; INR 3 lakh crore has already been allocated and about INR 6 lakh crore remains to be allocated, with the remaining projects to be allocated by '29 given an execution time of about 2 to 3 years.
    Show source
    So about 6 lakh projects will - - are still to be allocated, which are to be completed by 2032.
  • The remaining transmission projects are expected to be allocated in the next 4 years.
    Show source
    So, these all balanced transmission projects are to be allocated.
  • The Leh and Kaithal project is worth INR 20,000 crore plus, of which INR 12,000 crores to INR 13,000 crores will be for the HVDC portion and the balance for the transmission line; Khavda to South Olpad is not in hand.
    Show source
    So, you know that this Leh and Kaithal is INR 20,000 crore plus.
  • POWERGRID's Navsari digital substation connects Navsari to Magarwada, Kala and Ahmedabad in Gujarat, and to Padghe in Maharashtra.
    Show source
    And within Gujarat also, Navsari to Magarwada, Navsari to Kala, Navsari to Ahmedabad, Navsari to Padghe in Maharashtra.
  • POWERGRID's digital technology using fiber cables will make the risk of maloperation from EMI and EMC interference almost negligible.
    Show source
    So, if we use fiber cables and digital technology, the challenge or risk of maloperation will become almost negligible.
  • POWERGRID is working on two more skill development centers, one at Rajgad and one at Rourkela in Odisha.
    Show source
    Apart from these 3, we are also working on 2 more skill development centers, one at Rajgad, one at Rourkela in Odisha.
  • POWERGRID uses prefabricated firewalls for transformers and reactors and prefabricated cable trenches to minimize execution time at site.
    Show source
    Page 6 of 24 Power Grid Corporation of India Limited For expediting substation construction, we are using prefabricated firewalls for transformers and reactors and cable trenches are also prefabricated so that execution time at site is minimized.
  • POWERGRID identified HVDC projects from Khavda to Nagpur, Fatehgarh to Bhadla, Leh to Pang, Khavda to South Olpad, Rajasthan to Maharashtra, and Kurnool to Vizag; the Khavda to South Olpad project was already under bidding.
    Show source
    Then, we have one more already under bidding from Khavda to South Olpad.
  • POWERGRID was executing the HVDC Leh-Ladakh project, had acquired land at Leh, had infrastructure development work underway there, and was working on a line between Pang and Leh.
    Show source
    As far as the Leh-Ladakh project is there, it is already being executed by POWERGRID.
  • Preliminary studies for the Paradeep-Andaman-Singapore HVDC line had been completed; the Government of India was working out capacity between Paradeep and Andaman, and the line was expected to continue to Singapore while the modalities were being worked out.
    Show source
    For Paradeep Andaman and Singapore, preliminary studies have been already done.
  • South Olpad is a VSC project; Barmer to Maharashtra and Kurnool to Vizag are expected to be LCC projects, while VSC projects are expected for links between countries such as India to Oman, Oman to UAE, or Singapore to India.
    Show source
    Tyagi: South Olpad is VSC and Barmer to Maharashtra, it is likely to be LCC as of now.

Demand and pricing

  • POWERGRID maintained a minimum return on equity level of more than 12% or 13% for TBCB projects and said it was winning projects while maintaining that level.
    Show source
    Tyagi: No. intensity in the sense that like we are not going below a certain level that we have fixed a particular level that where maybe more than 12% or 13% ROE.

Segments

  • POWERGRID operates about 84% of the inter-regional transmission network.
    Show source
    And we operate about 84% of inter-regional transmission network.
  • POWERGRID was established in 1989 as India's flagship transmission utility.
    Show source
    As you know, that POWERGRID is India's flagship transmission utility, which was established in 1989.
  • POWERGRID's share of inter-regional capacity is almost 84%.
    Show source
    Our share is almost 84%.
  • POWERGRID uses bulk procurement to procure strategic equipment, including transformers, GIS, conductor, insulator and tower material, in advance because there is huge demand for this equipment.
    Show source
    For strategic equipment like transformers, GIS, conductor, insulator, tower material because there is a huge demand for this equipment, so we have adopted bulk procurement strategy to procure in advance so that we have these equipment well in advance to take care of any project or execution.
  • Management said there is no difference between inter-state and intra-state TBCB projects, and that more states are discussing TBCB projects, which are expected to come in many numbers.
    Show source
    So, there is no difference between inter- state transmission TBCB project and Inta State TBCB project.

Risks, rules and outside factors

Risks and disputes

  • POWERGRID's transmission line is not dependent on whether a PPA is signed; it receives tariffs once it commissions a project, so POWERGRID will not be affected by delays to RE projects or unsigned PPAs.
    Show source
    POWERGRID as such will not be affected by any of these issues.
  • POWERGRID said it would claim the differential compensation amount under change of law because compensation policies had changed since the projects were awarded, and it did not expect much impact from the delays or expenditure incurred on the schemes, though some impact was possible.
    Show source
    So whatever differential amount will be there, will be claiming under change of law.

Rules and policy

  • In June 2024, the Government of India increased ROW land compensation from 15% to 30% and tower base compensation from 85% to 200%; the policies were to be adopted by various states.
    Show source
    Considering requests or demands or resentment of farmers, so from 15% ROW land compensation, it was increased to 30%.
  • A delay between the Government of India's issuance of ROW guidelines and their adoption by state governments delayed execution or completion of transmission projects; in March 2025, the Government of India increased ROW compensation from 30% to 60% in urban areas and to 45% in semi-urban areas, and issued a methodology for land compensation using two valuers, one appointed by the transmission developer and one by the farmers.
    Show source
    Again, in March 2025, Government of India has again increased compensation, and from 200% and this ROW has increased to 60% from 30% in urban areas and in semi-urban areas, it has increased to 45%.

Everything else said on the call

People and governance

  • Smt. Sajal Jha recently joined the POWERGRID Board as a woman Independent Director.
    Show source
    I'm happy to announce that today, we have been enriched by woman Independent Director, Smt. Sajal Jha, who has recently joined POWERGRID Board.

Other

  • POWERGRID was benchmarked in quadrant 1 in ITOMS 2025, meaning its cost was low and its performance was high.
    Show source
    We have been benchmarked in quadrant 1, which means that our cost is low, our performance is high.
  • POWERGRID's Bassi Skill Development Center was recently opened on 1st May 2025.
    Show source
    And Bassi Skill Development Center has been recently opened on 1st May 2025.
  • India is targeting about $10 trillion economy by 2032 with rapid industrialization, urbanization and e-mobility adoption.
    Show source
    As you know that India is targeting about $10 trillion economy by 2032 with rapid industrialization, urbanization and e-mobility adoption.
  • Energy storage expansion will be about 47 GW by 2032; Pump Hydro Storage is about 36 GW, and clean energy commitments are more than 600 GW by 2032, with present capacity of 71 GW and additional electricity demand on account of Green Hydrogen production by 2032.
    Show source
    Energy storage expansion will be about 47 GW by 2032.
  • POWERGRID monitors all stations remotely from a control center at its Gurgaon headquarter, with cameras fitted at the stations.
    Show source
    We are monitoring all the stations from remote control center in Gurgaon headquarter, which all stations are fitted with the cameras, and we are monitoring, including CMD POWERGRID and Director (Projects).
Show 2 more statements

Other

  • POWERGRID opened three skill development centers, at Malda, Banka in Bihar and Bassi in Rajasthan; two batches had passed training at Malda and Banka and had been deployed or employed in the transmission-line industry.
    Show source
    Considering shortage of skilled manpower, we have opened 3 Skill development centers, one at Malda, one at Banka in Bihar and one at Bassi in Rajasthan, which is close to Jaipur.
  • POWERGRID was ranked among the best performers in transmission lines, transformers, circuit breakers, control and protection. Replaced by a later filing.
    Show source
    We have been ranked the best performers in transmission lines, transformers, circuit breakers, control and protection.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Sumit Kishore: I'm Sumit Kishore from Axis Capital. My first question is you have had a terrific year in terms of TBCB project wins of almost INR 92,000 crores. What is the transmission bid pipeline for this current financial year? And secondly, you had a capitalization miss versus what was guided earlier. So, if you could state what is the picture today in terms of the spillovers of commissioning, which have happened maybe early this fiscal, and what is your guidance for FY '26-'27 in terms of capitalization, given that you have provided capex numbers for FY '26, '27, '28? That is the first part of the -- yes.

    Answer, r.k tyagi

    R.K. Tyagi: Yes. thank you, Kishore. Like as we mentioned that in financial year, 2024-25, we had capex of about INR 26,000 crore plus and INR 9,000 crores plus capitalization. So, we had a plan for about INR 16,000 crores to INR 17,000 crores capitalization. So, because of this, there are challenges of RoW and supply issues and skill manpower, we are facing problems of skilled manpower. Page 14 of 24 Power Grid Corporation of India Limited And then there was election also in Central Government. So because of that, there have been some delays especially RoW issues in Rajasthan, Haryana, Delhi and Gujarat, so that led to some delays in this capitalization of or commissioning of some projects, which are now planned to be commissioned in quarter 1 of FY 2025-26.

    Answer, r.k tyagi

    And some may go in quarter 2 also. In financial year 2025-26, we are expecting about INR 23,000 crores to INR 25,000 crores capitalization.

  2. Question

    Sumit Kishore: Sir, also on the bid prospect pipeline for FY '26.

    Answer, r.k tyagi

    R.K. Tyagi: Yes, it is a pipeline, the projects which are already in pipeline is about INR 45,000 crore to INR 46,000 crore, out of which about INR 34,000 crore projects are already under bidding and INR 10,000 crore to INR 11,000 crore projects are yet to be bid. So, INR 46,000 crore you can say as of now.

  3. Question

    Sumit Kishore: But this is significantly lower after you won almost INR 92,000 crores of contracts last year. So may be this would be a slower year in terms of building new jobs into your works in hand.

    Answer, r.k tyagi

    R.K. Tyagi: This is as of now, but more projects are in pipeline, visibility of those projects will be seen after maybe 2, 3 months.

  4. Question

    Sumit Kishore: Sir, one question at the sector level is that we have seen that there was a bunching up of a lot of RE projects where LOAs were awarded, but PPAs were not signed and power demand so far this financial year has also started on a weak note. So, in the event, what is the impact on POWERGRID’s capitalization in case there is a large pipeline of projects where in RE, which were planned to be added, but those are obviously getting delayed? So how does that impact works in hand for POWERGRID? That's the question.

    Answer, r.k tyagi

    R.K. Tyagi: Our transmission line is not dependent on whether PPA is signed or not. Normally, we are given any project for which a separate timeline is given. Once we commission any RE project or any project for that matter, we start getting our tariffs. So, we are not having any risk of whether RE is delayed or PPA is signed or not. POWERGRID as such will not be affected by any of these issues. Page 15 of 24 Power Grid Corporation of India Limited Sumit Kishore: Fair enough.

  5. Question

    So just if I may ask one last question. So, your ROE has dipped by about 100 basis points at the consolidated level this year with the various issues that we have been discussing so far. Has the ROE stabilized here now with all the issues baked in and what is the outlook? And the capital structure, which is at 59:41. So how do you see this evolving? So given your dividend per share has also come off at INR 9 on a year-on-year basis.

    Answer, r.k tyagi

    R.K. Tyagi: As far as dividend is concerned, like we have -- as you know, that we have more projects now. So, we require equity for our project execution. So that is why our dividend payout is reduced by about INR 2 – INR 2.25. So, we will require more money in future. So may be next year also, there may be some change from INR 9. It can further reduce depending on the capex, which we are expecting, say, about INR 28,000 crores to INR 30,000 crores.

    Answer, r.k tyagi

    So that was the reason why we have reduced our dividend payout. As far as this ROE impact, last year, we had INR 15,500 crores. And this year, also, our profit is again in the same range, but our Net Worth has increased from INR 87,000 crore to about more than INR 90,000 crores. So that is the reason why you can see that impact.

  6. Question

    Apoorva Bahadur: Quickly, sir, I wanted to understand and know your view over here, you highlighted that the company has INR 92,000 crores worth of projects in FY '25. I assume this is the NCT cost and how much higher do you expect the actual cost to be over here?

    Answer, r.k tyagi

    R.K. Tyagi: Yes. It is not NCT cost. It is our internal cost, at which we have awarded the projects.

  7. Question

    Apoorva Bahadur: Okay. Sir, secondly, do -- has there been any change in the competitive intensity for TBCB projects for the bids now, given that the overall pie had increased significantly last year?

    Answer, r.k tyagi

    R.K. Tyagi: No. intensity in the sense that like we are not going below a certain level that we have fixed a particular level that where maybe more than 12% or 13% ROE. So, we are maintaining that and maintaining that whatever projects we are able to win, we are winning and our percentage is very good. As you can also appreciate INR 92,000 crore projects in a single year is not a small thing. So - - but still, we are maintaining our ROE above the particular level.

  8. Question

    Apoorva Bahadur: Sir, last question from my side. on the HVDC projects, can you give us some visibility beyond the 3 or 4 projects that are known as of now? How many more are under planning?

    Answer, r.k tyagi

    R.K. Tyagi: As far as this HVDC project, like we have this Khavda to Nagpur, then we have Fatehgarh to Bhadla. We have this Leh to Pang. Then, we have one more already under bidding from Khavda to South Olpad. Then, one more project from Rajasthan to Maharashtra. Then, one more project in Andhra from Kurnool area to Vizag. So, these are, as of now, within India, maybe outside India, maybe between India to Singapore via Andaman.

    Answer, r.k tyagi

    Then, maybe from India to Sri Lanka and India to Myanmar. Apart from this side, One Sun, One World, One Grid may be from India to Oman, UAE and other countries.

  9. Question

    Satyadeep: Just first question on the delays that were seen in the fourth quarter. I think elections and all, I know happened towards the earlier part of the year. But in 3Q, management was guiding to INR 11,000 crores of capitalization in 4Q. So, I just wanted to understand what is leading to some of these delays. And given the large difference between capex and capitalization, obviously, you're incurring the capex, but there is some delay in commissioning of the project, which means you've already acquired land, maybe already base suppliers, but maybe there is some delay in actual commissioning. And how does it impact your actual commissioning cost and time line versus what you were expect

    Answer, r.k tyagi

    R.K. Tyagi: Let us accept that there are challenges of ROW and because everyone, including landowners and farmers, they are demanding more and more money. Our Government of India is also considerate to their demands. And you may be knowing that in June 2024, there was a ROW guideline issued by Government of India. Considering requests or demands or resentment of farmers, so from 15% ROW land compensation, it was increased to 30%. And on tower base, it was increased from 85% to 200%. And these schemes were like these policies, ROW compensation policies are to be adopted by various states.

    Answer, r.k tyagi

    So, there is some delay between adoption of these guidelines from issuance by Government of India to adoption by state government. So that leads to a delay in execution or completion of transmission projects. Then again, in -- there was unrest in Haryana and Delhi. Again, in March 2025, Government of India has again increased compensation, and from 200% and this ROW has increased to 60% from 30% in urban areas and in semi-urban areas, it has increased to 45%. And now they have clearly indicated how to give the price to the farmers or cost to the farmers for land compensation. So that methodology also shared by Government of India, guideline has been issued. As per that, 2 valuers will be there, one by the transmission developer, one by the farmers.

    Answer, r.k tyagi

    And that they will decide the market rate. And we will have to pay land compensation as per the market rate. So, there has been some delays because of these ROW compensation policies issued by Government of India and adoption by State Government. So, in 2024-25, there has been delays in some projects. But we are expecting that in 2025-26 since already guidelines are in place. So, the execution will be much faster as compared to FY 2024-25. And as far as you are seeing impact on the return on equity or our return, what will happen to time overrun and cost-overrun.

    Answer, r.k tyagi

    Page 18 of 24 Power Grid Corporation of India Limited So, we are likely to get these claims under change of law because, as on date, when we got these projects, we were adopting the compensation policies issued in October 2015. So, we have considered that compensation policy, but now compensation policies have been changed. So whatever differential amount will be there, will be claiming under change of law. So, we are not expecting impact of any delay or our expenditure incurred on these schemes. So, we are not expecting much impact. There may be some impact but not much impact. Satyadeep: Okay.

    Answer, r.k tyagi

    Thank you for clarifying that. Second question on the pipeline. So, in the INR 3 lakh crore pipeline that you have, you obviously have INR 270,000 crores of ISTS, that I'm sure there's some maths involved in that based on NEP estimates and some market share. But also just on that, given the previous speaker also asked the question on that, if the -- ultimately the DISCOM has to bear that cost, if you commission the project, but there is no RE, would you sense some pressure from DISCOMs to delay some of these projects, if the RE player has requested connectivity under GNA, but there are some delays? Would you not expect some requests from DISCOMs to delay these projects? And given there is change in GNA regulations on battery, solar or non solar, do you see some risk to these estimates you have, just wanted to see sensitivity and maybe is there any risk to these capex expectations that you have?

    Answer, r.k tyagi

    R.K. Tyagi: As we have indicated that a $10 trillion economy by 2032 and in transmission itself as per NEP issued by Government of India, National Electricity Plan for transmission, about INR 10 lakh crore are to be spent in transmission system development. So out of which, INR 3 lakh crore is, I think it is very, very optimistic figure. So, it may be more. So, we are not seeing any challenge or any issue in achieving this target.

  10. Question

    Mohit: So, my question is what is the status of the HVDC Leh-Ladakh. And why there is a delay in awarding of the equipment? That's the first question.

    Answer, r.k tyagi

    R.K. Tyagi: Yes. Please, carry on. Page 19 of 24 Power Grid Corporation of India Limited Mohit: My second question is on the, what is the status of Paradeep-Andaman link. I think it was supposed to be awarded to us on a cost-plus basis. Are you expecting this project to get added to the pipeline in FY '26?

    Answer, r.k tyagi

    R.K. Tyagi: Okay. As far as the Leh-Ladakh project is there, it is already being executed by POWERGRID. We have already acquired land at Leh. And the infrastructure development work is already going on there. And we are also working for a line between Pang to Leh. So that's also there.

    Answer, r.k tyagi

    But as far as award of HVDC is concerned because you will appreciate that height is about 4,500 meters to 5,000 meters. So, there are technological challenges. And worldwide, there is no experience at this height. So that have been concerns raised by various bidders, and there have been some discussion with our experts. We have technical experts and advisors team. So, we are addressing those issues with our prospective bidders. And now we are now expecting that it will be awarded somewhere in -- we have already got the bid, which is under evaluation.

    Answer, r.k tyagi

    And in quarter 2, it is likely to be awarded. So, I think it will not be further delayed after quarter 2. For Paradeep Andaman and Singapore, preliminary studies have been already done. And Government of India is working out the capacity between this Paradeep to Andaman. And same line -- HVDC line is likely to be like maybe between Singapore to India. So same line will continue to Singapore also. Those modalities are being worked out by Government of India.

    Answer, r.k tyagi

    And then, once the Government of India comes out with a clear methodology, then we will consider this project also. So as of now, there is no clear visibility. Maybe in quarter 2, there will be some clear visibility by Government of India.

Show 8 more questions
  1. Question

    Puneet: My first question is if you can talk what is gap between the NCT value and your own estimates for the projects that you have won?

    Answer, r.k tyagi

    R.K. Tyagi: Yes. Except for HVDC project, which we have between Khavda to Nagpur, so maybe others are almost matching maybe -- within 5% variation maybe there. But in this particular case, cost -- NCT cost is about INR 24,000 crores, but actual cost may be INR 33,000, INR 34,000 crores. Otherwise, other projects are within 5%. Puneet: Understood. That's very helpful.

    Answer, r.k tyagi

    R.K. Tyagi: Normally, this also because it will impact IDC. So, we are likely to get this also, and we will claim also that whatever -- because of delay there have been project overrun and IDC has increased. So, we will claim that amount also.

  2. Question

    Subhadip Mitra: My first question is with regard to the HVDC TBCB pipeline. So, the South Olpad project is expected to come into the tendering phase by when?

    Answer, r.k tyagi

    R.K. Tyagi: Yes, it is already under -- RFP has already been issued and bids are likely to be submitted very soon. So, there was a date of 16th May, which has been increased now because of some, they've got some queries from the prospective bidders. So, it will be like -- a tender is already out and RFP is already out, and it will be -- very soon it will be finalized.

  3. Question

    Subhadip Mitra: Understood. And secondly, are we seeing more HVDC projects, maybe the Barmer project or any other LCC based projects coming up after South Olpad?

    Answer, r.k tyagi

    R.K. Tyagi: South Olpad is VSC and Barmer to Maharashtra, it is likely to be LCC as of now. And this -- the Andhra Pradesh also Kurnool to Vizag is also LCC. VSC as of now, only between 2 countries like if it is India to Oman or Oman to UAE or maybe between Singapore to India, that will be VSC.

  4. Question

    Sir, any idea about likely capex on Paradeep, Andaman, Singapore link, what will be the rough size of the project?

    Answer, r.k tyagi

    R.K. Tyagi: As per initial estimates, I cannot say exactly, but it will be INR 30,000-plus crore.

  5. Question

    Atul Tiwari: And what will be the capacity roughly for that capex?

    Answer, r.k tyagi

    R.K. Tyagi: Capacity, if it is, say, between Singapore to India, it may be about 2,000 MW. But between Andaman to Paradeep, it will be about, say, 250 MW. Atul Tiwari: Okay. And sir, in terms of the TBCB pipeline, you did mention about INR45,000 crores as you can see right now. But if you take a slightly longer- term view FY '27 and '28, over next 3 years, what is the likely pipeline for TBCB that will be bid for?

    Answer, r.k tyagi

    R.K. Tyagi: Yes. So as far as this NEP -- as per NEP pipeline, more than INR 9 lakh crore projects are to be completed by in 2032. So out of which already 3 lakh projects are already -- they have been already allocated. So about 6 lakh projects will - - are still to be allocated, which are to be completed by 2032. So, considering execution time of about 2 to 3 years. So, by '29, all balanced projects are to be allocated.

    Answer, r.k tyagi

    So, you can consider that in the next 4 years. So, these all balanced transmission projects are to be allocated. So, you can calculate yourself.

  6. Question

    Sumit Kishore: So, thank you so much for the opportunity once again. So, my question is that in terms of the in terms of your capex over FY '26 to '28, it adds up in terms of guidance to about INR 1,080 billion as compared to your works in hand of roughly about INR1,546 billion. So, in this INR1,080 billion, how much is the capex that you are planning to incur for the HVDC projects, which have typically a longer gestation period and I'm referring to the larger ones, including the Leh project?

    Answer, r.k tyagi

    R.K. Tyagi: Yes. We have mentioned that we have about INR 1,54,000 crore projects in hand, and say, about INR 28,000 crores in FY 2025-26 and INR 35,000 crores in '26-'27 and '27-'28, INR 45,000 crore, which adds up to, say, about INR 108,000 crores or INR 110,000 crores. So, balance will be for HVDC, which will be this Kaithal to Pang and HVDC Khavda to Nagpur. So, majority Page 22 of 24 Power Grid Corporation of India Limited of this capex for HVDC will be after 2 years only. So, we will have some maybe 20% or 30% up to 2027-'28, but balance will be after 2 years only.

  7. Question

    Sumit Kishore: Sir, what will be the total value of the HVDC contracts under VSC or LCC route that you're looking to award 2 contractors in the next 1 year or next 2 years, typically VSC and LCC, if you can give separately, that will be very useful for FY '26 and FY '27.

    Answer, r.k tyagi

    R.K. Tyagi: We can tell only like we have only 1 project in hand, which is Leh and Kaithal and balance this Khavda to South Olpad, it is not in hand. So, we cannot talk anything about that unless until we win that. So, you know that this Leh and Kaithal is INR 20,000 crore plus. So out of which maybe INR 12,000 crores, INR 13,000 crores will be for HVDC portion. Balance will be for transmission line. So that only I can confirm as of now.

    Answer, r.k tyagi

    Balance -- once we win these projects, then only we can say LCC or VSC or...

  8. Question

    Puneet: If you can also talk about the potential opportunity on the inter -- intra-state transmission side. Is that opening up? Or is it still largely done by state transcos?

    Answer, r.k tyagi

    R.K. Tyagi: No. Intra-state, as per NEP, they have shown that they have indicated that there will be expenditure or capex of about INR 3 lakh crore plus in intra-state. So now unless until they go under TBCB execution, then only it can be achieved. So otherwise, INR 3 lakh crore will be very difficult to be achieved by various states. So UP, MP, then Rajasthan, then Odisha, Maharashtra, these states have already come out with this intra-state TBCB projects. So, we are also participating with the same interest as compared to inter-state TBCB project. So, we are also expecting that we will also win some projects in intra-state transmission system also.

    Answer, r.k tyagi

    So, there is no difference between inter- state transmission TBCB project and Inta State TBCB project. And more and more states are talking these days by -- for TBCB projects. So, they will come in many numbers. All the states should follow this intra-state TBCB. Puneet: Any size you can give for this current tenders?

    Answer, r.k tyagi

    R.K. Tyagi: As of now, no, I may not be in a position to share any figure. Page 23 of 24 Power Grid Corporation of India Limited Moderator: Ladies and gentlemen, that was the last question for today.

    Answer, r.k tyagi

    R.K. Tyagi: Yes. I once again thank each and every one of you for joining and taking interest in POWERGRID. POWERGRID’ s management is committed to achieve all the targets, which we have mentioned today. And regarding project efficiency, operational efficiency, we will be working very hard to achieve all the targets given by Government of India. Thank you once again for showing your interest, thank you.

Questions about this call

When was the Power Grid Corporation of India Q4 FY25 earnings call transcript filed?
Power Grid Corporation of India filed the transcript with the exchange on 28 May 2025. This page is built from that transcript.
What does this page list?
106 statements from the transcript across 11 topics, 89 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 18 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.