Earnings call
Power Grid Corporation of India Q3 FY26 earnings call: POWERGRID received one multi-year telecom order worth ₹206 crores in Q3 FY 2025-26
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
POWERGRID received one multi-year telecom order worth ₹206 crores in Q3 FY 2025-26. POWERGRID had achieved ₹29,200 crores of CapEx and expected to exceed ₹32,000 crores of CapEx by March 2026, after crossing its ₹28,000 crores target agreed with the Government of India. POWERGRID said it would shortly start one 400kV and 220kV project in Kenya with Africa50. POWERGRID achieved its 50% renewable power-consumption target by December 2025. Under the NEP guideline, there were almost 3 lakh crore of intra-state projects, of which only a few had been awarded so far.
The numbers management gave
Results
- POWERGRID achieved its 50% renewable power-consumption target by December 2025.
Show source
By 2025 December we have achieved this target. - As you know that POWERGRID is a Government company, in which Government of India holds major shareholding, 51.34%, then FII is about 24.73%, domestic DII is 20.26%.
- POWERGRID’s annual tripping per line was 0.21, comparable with or better than international best utilities.
Show source
And our reliability or annual tripping per line is also comparable or better than int ernational best utilities, which is 0.21 tripping per line. - For taking care during emergencies, disasters we have mobile substation similar to transmission line where we have emergency restoration system.
- POWERGRID’s standalone revenue or income increased 4% to ₹35,041 crores in nine months from ₹33,843 crores.
Show source
If we talk of nine-months revenue or income, it has increased from ₹33,843 crores to ₹35,041 crores on standalone basis; there is increase of 4%.
- POWERGRID’s profit after tax increased 7% to ₹4,160 crores in Q3 FY26 from ₹3,894 crores in Q3 FY25.
Show source
And after considering expenses, depreciation and other things, our Profit After Tax for Q3 has increased from ₹3,894 crores to ₹4,160 crores, which is increase of 7% in Q3FY26 versus Q3FY25. - And if we talk of nine-months, it has increased from ₹11,017 crores to ₹11,368 crores; there is an increase of 3 %. - On consolidated basis, Income has increased from ₹11,743 crores to ₹12,599 crores; there is an increase of 7 %.
- POWERGRID’s profit after tax increased 3% to ₹11,368 crores in nine months from ₹11,017 crores.
Show source
And after considering expenses, depreciation and other things, our Profit After Tax for Q3 has increased from ₹3,894 crores to ₹4,160 crores, which is increase of 7% in Q3FY26 versus Q3FY25. - And if we talk of nine-months, it has increased from ₹11,017 crores to ₹11,368 crores; there is an increase of 3 %. - On consolidated basis, Income has increased from ₹11,743 crores to ₹12,599 crores; there is an increase of 7 %.
- POWERGRID’s consolidated income increased 7% to ₹12,599 crores from ₹11,743 crores.
Show source
And after considering expenses, depreciation and other things, our Profit After Tax for Q3 has increased from ₹3,894 crores to ₹4,160 crores, which is increase of 7% in Q3FY26 versus Q3FY25. - And if we talk of nine-months, it has increased from ₹11,017 crores to ₹11,368 crores; there is an increase of 3 %. - On consolidated basis, Income has increased from ₹11,743 crores to ₹12,599 crores; there is an increase of 7 %.
Show 29 more statements
Results
- POWERGRID’s consolidated income increased 2% to ₹35,714 crores in nine months from ₹34,869 crores.
Show source
And in nine-months also there is increase from ₹34,869 crores to ₹35,714 crores; there is an increase of 2 %.
- POWERGRID’s profit after tax increased 8% to ₹4,185 crores from ₹3,862 crores.
Show source
And Profit After Tax is 8% increase, that is ₹3,862 crores and it has Page 5 of 23 become ₹4,185 crores.
- POWERGRID’s profit after tax increased nominally to ₹11,382 crores in nine months from ₹11,379 crores because it received one-time income in the prior year.
Show source
But in nine-months, because last year we got some special income, from ₹11,379 crores it has increased to ₹11,382 crores, which is nominal increase only.
- POWERGRID’s earnings per share increased to ₹12.24 from ₹12.23.
Show source
Earnings Per Share is ₹12.23 and now it is ₹12.24.
- POWERGRID’s book value per share was ₹106.34, compared with ₹98.51 last year.
Show source
And book value per share is ₹106.34 as against ₹98.51 last year.
- POWERGRID’s return on net worth was 11.51%, compared with 12.42%, because net worth increased while profit was almost the same.
Show source
And Return on Net Worth is 11.51% as against 12.42% because the Net Worth has increased and profit is almost same. - These are some key financial information.
- POWERGRID’s income from the previous period increased to ₹509 crores from ₹63 crores.
Show source
The income from previous period, from 63 crores it has become 509 crores.
- POWERGRID earned ₹95 crores of interest on differential tariff, compared with ₹102 crores.
Show source
Interest on differential tariff ₹95 crores as against ₹102 crores.
- POWERGRID earned ₹802 crores of interest from subsidiaries and JVs, compared with ₹560 crores.
Show source
Interest from subsidiaries and JVs ₹802 crores as against ₹560 crores.
- POWERGRID earned ₹239 crores in incentives, compared with ₹150 crores.
Show source
Incentive – ₹239 crores as against ₹150 crores.
- POWERGRID received ₹22 crores in dividends from JVs.
Show source
And dividend from JVs – ₹22 crores.
- POWERGRID received ₹347 crores in dividends from subsidiaries.
Show source
Dividend from subsidiaries – ₹347 crores.
- POWERGRID’s CSR expenses were ₹130 crores, compared with ₹161 crores.
Show source
CSR expenses ₹130 crores against ₹161 crores.
- POWERGRID’s telecom income increased from ₹825 crores to ₹879 crores in Q3 FY 2025-26.
Show source
In Telecom, our income has increased from ₹825 crores to ₹879 crores.
- POWERGRID’s telecom network had more than 1 lakh kilometers of network in Q3 FY 2025-26.
Show source
And our telecom network is more than 1 lakh kilometers.
- POWERGRID’s consultancy income increased from ₹427 crores to ₹1,173 crores in Q3 FY 2025-26.
Show source
In Consultancy, the income has increased from ₹427 crores to ₹1,173 crores.
- The company achieved 3,300 ckm against its annual target of 5,500 ckm in Q3 FY 2025-26; it achieved 42,000 MVA against its target of 60,000 MVA.
Show source
Our target, annual target is 5500 ckm, circuit kilometer, out of which we have achieved , already achieved 3300 ckm.
- The company reported capitalization of only 12,000 crores in Q3 FY 2025-26.
Show source
In Q3FY26 also, you can see that it was only 12,000 crores capitalization.
- POWERGRID's CapEx was ₹26,000 crores last year.
Show source
Last year, we had ₹26,000 crores.
- POWERGRID has maintained transmission system availability above 99.75%; availability was 99.82% last year and 99.84% so far in Q1 FY 2025-26.
Show source
Our transmission system availability is 99.84%.
Money and capital
- POWERGRID’s gross fixed assets crossed ₹3 lakh trillion for the first time.
Show source
For 2024-25 again, like all the years, last so many years we have been achieving M oU rating of ‘Excellent’ by Government of India, Department of Public Enterprise. - As I told that gross fixed assets , for the first time it has crossed ₹3 lakh trillion.
- POWERGRID’s CapEx for nine months was ₹26,761 crores, compared with ₹17,651 crores.
Show source
In nine- months our CapEx has been ₹26,761 crores as against ₹17,651 crores.
- POWERGRID’s standalone gross fixed assets increased to ₹2,69,000 crores from ₹2,63,000 crores.
Show source
So, there was one-time income last year. - In financial performance, our gross fixed assets on standalone basis has increased from ₹2,63,000 crores to ₹2,69,000 crores.
- POWERGRID’s consolidated gross fixed assets increased to ₹3,04,000 crores from ₹2,88,000 crores.
Show source
On consol basis, it has increased from ₹2,88,000 crores to ₹3,04,000 crores.
- POWERGRID’s capital work in progress increased to ₹50,000 crores from ₹29,000 crores.
Show source
Capital work in progress, it has increased from ₹29,000 crores to ₹50,000 crores work in progress.
- POWERGRID’s debt increased to ₹1,43,000 crores from ₹1,29,000 crores because more projects were underway.
Show source
Our debt has increased from ₹1,29,000 crores to ₹1,43,000 crores because number of projects are going on now.
- POWERGRID’s net worth increased to ₹98,000 crores from ₹91,000 crores.
Show source
Our Net Worth, as I told, it has increased from ₹91,000 crores to ₹98,000 crores.
- POWERGRID maintained a debt/equity ratio of 59:41.
Show source
Our Debt/Equity ratio is 59:41 maintained.
- The company has ₹32,000 crores for FY26.
Show source
Tyagi – Chairman & MD: - Like I told that, we have now ₹32,000 crores for FY26.
What it expects ahead
What management expects
- POWERGRID had achieved ₹29,200 crores of CapEx and expected to exceed ₹32,000 crores of CapEx by March 2026, after crossing its ₹28,000 crores target agreed with the Government of India.
Show source
We have already achieved ₹29,200 crores CapEx and we have target to exceed ₹32,000 crores CapEx this year by March 2026. - In capitalization, in nine -months we capitalized assets worth ₹12,915 crores as against ₹7,423 crores last year.
- 600 GW of non-fossil fuel power capacity is going to be added by 2032.
Show source
We know that by 2032, 600 GW of non-fossil fuel capacity, power capacity , is going to be added.
- By 2032, India will have 47 GW of BESS, that is Battery Based Energy Storage, and 27 GW of Pump hydro.
Show source
Then, 71 GW will be additional electricity demand only for Green hydrogen by 2032. - In Energy Stor age, we have 47 GW BESS, that is Battery Based Energy Storage, by 2032, and Pump hydro 27 GW.
- Battery storage would normally be 10 to 15% of total generation capacity.
Show source
So, normally it is 10 to 15% of the total generation capacity. - Mr. Apurva – IIFL: - Understood.
- The company expects to achieve almost 1,500 to 2,000 ckm by the end of this financial year.
Show source
We have already achieved 42,000 MVA and we are sure that we will be achieving almost 1500 to 2000 ckm by end of this financial year.
- The company expects to add almost 18,000 to 20,000 MVA capacity in the next two months and be very close to its target of 60,000 MVA capacity.
Show source
So , we will be very close to the target which has been gi ven by CEA or Government of India and similarly, in transformation also, we will have almost 18,000 to 20,000 MVA capacity will be added in next two months, so we will be very close to 60,000 MVA capacity. - In case of HVDC, there are only three manufacturers.
Show 24 more statements
What management expects
- The company has guidance of about 50 to 60% market share for new projects in this fiscal year.
Show source
We are about 50 to 60%.
- POWERGRID expects CapEx of ₹32,000 crores this year.
Show source
This year we are going to have ₹32,000 crores.
- POWERGRID expects capitalization of ₹22,000 crores this year.
Show source
Similarly, we will have capitalization also, like last year, it was not much, but this year it will be ₹22,000 crores.
- POWERGRID expects its projects in the next two to three years to be mainly TBCB, with 80% to 90% TBCB and 10% to 20% RTM.
Show source
So, I can say that 80 to 90% will be TBCB, 10 to 20% will be RTM. - Mr. Shirom Kapoor – Jefferies: - Got it sir.
- Battery energy storage projects in RTM may follow if the CERC draft document is approved or becomes available; the matter is under discussion.
Show source
And if once this, CERC draft document is approved or it is available, then there will be p rojects for battery energy storage in RTM also.
- The company expects intra-state projects to gain traction and is evaluating the risks associated with them as it proceeds.
Show source
So, we see that intrastate will be gaining traction.
- The company will decide how aggressively to bid for intra-state projects depending on its book position and the situation, because the projects are difficult.
Show source
So, depending on our book position, we will be aggressively or not aggressively bidding for those projects because being intra state project and very difficult projects.
- Capitalization depends on project commissioning and the size of each project; the percentage in a quarter will increase if a project comes in during Q4, Q1 or Q2, and projects will continue to be commissioned.
Show source
Tyagi – Chairman & MD: - Like, the capitalization depend on, the project being commissioned, i t depends on the size of that particular project.
- POWERGRID said it was poised to exceed its annual guidance. Replaced by a later filing.
Show source
I can assure you that we are poised to exceed our annual guidance, which we have been talking.
- POWERGRID will be aggressively participating in Battery Energy Storage projects likely to be bid out. Replaced by a later filing.
Show source
So, POWERGRID will be aggressively participating in those projects also. - In Kenya, as you know that, we have recently signed this PPP model project, transmission project, which involves transmission line from Loosuk to Lessos.
- Progress is increasing, and Q3 and Q4 progress will be better. Replaced by a later filing.
Show source
So now in Q3, Q4 progress will be better. - Mr. Nikhil – Bernstein: - So would you say it's not a temporary change we have seen?
- POWERGRID's capitalization will increase next year. Replaced by a later filing.
Show source
Next year, again it will increase.
Orders
- POWERGRID received one multi-year telecom order worth ₹206 crores in Q3 FY 2025-26.
Show source
We have received one order worth ₹206 crores, this is a multi-year order.
- POWERGRID had 5 new consultancy orders and 77 ongoing consultancy orders in Q3 FY 2025-26.
Show source
New orders; we have 5 numbers, ongoing 77.
- POWERGRID had 2 international orders and 14 ongoing international orders in Q3 FY 2025-26.
Show source
Then international, we have 2 orders from international as well as ongoing 14 numbers.
- POWERGRID won the transmission system for evacuation of power from pumped storage projects in Sonbhadra, costing about ₹3,626 crores with tariff of ₹328.4 crores.
Show source
It is costing about ₹3,626 crores with tariff of ₹328.4 crores.
- POWERGRID won the inter-regional strengthening project between SR and ER for ₹2,723 crores with tariff of ₹311.9 crores.
Show source
It is ₹2,723 crores with tariff of ₹311.9 crores.
- POWERGRID won the NR-WR Vindhyachal-Varanasi project involving the Prayagraj station, costing ₹2,368 crores with tariff of ₹323.1 crores.
Show source
• Between NR and WR, Vindhyachal-Varanasi, involving station of Prayagraj, the cost is ₹2,368 crores with tariff of ₹323.1 crores.
- POWERGRID won an intrastate transmission project in Maharashtra to remove transmission constraints in Pune, involving a 765kV /400kV substation in Pune East with a tariff of about ₹368.5 crores; its cost will be somewhere about ₹3,500 crores because it was not discussed in NCT, and NCT cost is not available.
Show source
So , cost will be somewhere about ₹3,500 crores .
- POWERGRID won the Davangere-Bellary project for ₹1,111 crores with tariff of ₹130 crores.
Show source
• Then Davangere-Bellary, ₹1,111 crores with tariff of ₹130 crores.
- POWERGRID won the transmission system in Davangere for ₹379 crores with tariff of ₹42.3 crores.
Show source
• Then transmission system in Davangere, ₹379 crores with tariff of ₹42.3 crores.
- POWERGRID won a 150 MW, 350 megawatt hours Battery Energy Storage project at Kalikiri, Andhra Pradesh, on a TBCB basis, with Build-Own-Operate basis and VGF support; its estimated cost is about ₹250 crores and annual tariff is ₹29.52 crores.
Show source
The estimated cost is about ₹250 crores and annual tariff is ₹29.52 crores. - We are also aggressively participating in the BESS projects.
- POWERGRID's projects amount to ₹1,45,000 crores, or ₹1,43,000 crores excluding ₹2,000 crores of projects for data center and other areas; most are TBCB projects, while ongoing RTM projects amount to about ₹9,000 crores to ₹10,000 crores.
Show source
If you see from the data that it is ₹1,45,000 crores, if we remove ₹2000 crores worth projects for data center and ot her areas, it becomes ₹1,43,000 crores.
- The company was recently successful in one of the largest intra-state projects in Maharashtra and is awaiting the LoI.
Show source
We have, as already as our C hairman has placed it, one of the largest intrastate project in the state of Maharashtra, is what we have recently been successful in it.
What it is building and selling
Projects and capacity
- POWERGRID said it would shortly start one 400kV and 220kV project in Kenya with Africa50.
Show source
One 400kV and 220kV project we will be starting shortly. - Considering energy storage in battery, we have ventured into first Battery Energy Storage project on Build-Own-Operate in Andhra Pradesh. - Towards ESG, we have recently commissioned first 400kV/220kV 315 MVA transformers using synthetic ester oil, which is a vegetable oil.
- POWERGRID has 1,83,174 circuit kilometer of transmission lines and 1,566 transmission lines.
Show source
It is 1,83,174 circuit kilometer with 1,566 number of transmission line.
- POWERGRID has 288 substations with 5,99,016 MVA capacity following the commissioning of Ahmedabad and Ananthapuram.
Show source
Our substations with the last commissioning of Ahmedabad and then Ananthapuram, it has increased to 288 with 5,99,016 MVA capacity.
- POWERGRID’s inter-regional power-flow capacity is approximately 101 GW.
Show source
Inter- regional capacity, that means power flow capacity from one region to another region, it is 101 GW (approx.).
- POWERGRID has a fleet of more than 4,000 transformers and reactors.
Show source
And transformers and reactors , we have fleet of more than 4,000 transformers and reactors.
- As of 31 January 2026, POWERGRID had commissioned projects worth ₹18,700 crores and targeted more than ₹22,000 crores, above its ₹20,000 crores target for the year.
Show source
And as on 31 st January, 2026, we have commissioned projects worth ₹18,700 crores and we have target of achieving more than ₹22,000 crores as against our target of ₹20,000 crores, which we committed during this year.
Show 50 more statements
Projects and capacity
- POWERGRID commissioned the 765 kV D/C Khetri-Narela line after 30 September 2025; it was a critical line for evacuating green energy from Rajasthan.
Show source
• 765 kV D/C Khetri-Narela, which was a very, very critical line for power evacuation, especially green energy from Rajasthan.
- POWERGRID commissioned the 765 kV D/C Ahmedabad-Lakadia and Ahmedabad-Navsari lines after 30 September 2025; the lines were required to evacuate power from Khavda area KPS1, KPS2 and KPS3.
Show source
• 765 kV D/C Ahmedabad- Lakadia and Ahmedabad-Navsari have been commissioned.
- POWERGRID commissioned the 765 kV D/C Bhadla II–Sikar II transmission line after 30 September 2025.
Show source
It has been commissioned.
- POWERGRID commissioned three 1,500 MVA transformers, together providing 4,500 MVA capacity, at Narela substation.
Show source
1500 MVA each capacity, so put together 4500 MVA.
- POWERGRID commissioned a 1,500 MVA transformer, ICT-6, at Khavda-II.
Show source
• Then Khavda-II, again 1 more transformer of 1500 MVA, ICT- 6.
- POWERGRID commissioned a 1,500 MVA 765/400kV transformer at Indore.
Show source
• Indore 1500 MVA 765/400kV.
- POWERGRID commissioned two 1,500 MVA ICTs at Dausa substations.
Show source
• And 2 numbers 1500 MVA ICT at Dausa substations.
- POWERGRID commissioned a 500 MVA transformer at Kurnool-III.
Show source
• In 400kV, at Kurnool-III 500 MVA.
- POWERGRID upgraded Bawana’s capacity from 315 MVA to 500 MVA to meet Delhi’s requirement.
Show source
• Then upgradation at Bawana from 315 MVA to 500 MVA for meeting requirement of Delhi.
- POWERGRID commissioned substations at Narela and Ananthapuram after 30 September 2025.
Show source
• And 2 station, Narela and Ananthapuram, have been commissioned since last 30th September. - In operations, as usual, we are always excellent.
- POWERGRID had procured a 220kV mobile GIS substation and ordered 132kV and 400kV units, which it expected to arrive shortly.
Show source
So, far we have only procured 220kV but 132kV and 400kV have been ordered and they will be also coming very shortly. - Financials: - In financials, our Total Income for nine-months is ₹35,714 crores, EBITDA ₹29,846 crores, Profit After Tax for nine-months is ₹11,382 crores, Net Worth is ₹98,906 crores, Gross Fixed A sset is ₹3,04,336 crores, our Debt/Equity Rati o is 59:41. - If we compare with last year Q3 FY25 to FY26 , Total Income has increased from ₹11,609 crores to ₹12,436 crores ; there is increase of 7%.
- POWERGRID had ₹1,45,513 crore works in hand, apart from ₹50,000 crore projects work in progress, in Q3 FY 2025-26.
Show source
Page 6 of 23 - As of today, we have ₹1,45,513 crore works in hand, apart from ₹50,000 crore projects work in progress.
- POWERGRID has ₹1,95,000 worth projects to be commissioned in the next 3-4 years.
Show source
So, we have ₹1,95,000 worth projects which are to be commissioned in next 3-4 years.
- Projects worth ₹55,000 crore are already under bidding, and projects worth ₹15,000 crore are approved but yet to be put up for bidding.
Show source
Projects are already under bidding, and there are about ₹15,000 crore projects which are approved but yet to be , up for bidding.
- An average of ₹90,000 crore of projects will be bid out each year.
Show source
So , there will be almost , on an average ₹90,000 crore projects each year will be bid out. - Mr. Shubhdeep – Nuvama: - So if I hear you correctly, out of six lakh sixty thousand crores till FY 32, three lakh is done.
- Projects worth ₹2,30,000 crores are already under execution or commissioned, and ₹55,000 crores are available for bidding.
Show source
Tyagi – Chairman & MD: - ₹2,30,000 crores is already under execution or commission ed, ₹55,000 crores up for bidding.
- Projects worth ₹15,000 crore are yet to be available for bidding, and projects worth ₹3,60,000 crores will be available for bidding in the next four years to be completed before 2032.
Show source
So those will be ₹3,60,000 crores in 4 years.
- The company has the Bikaner, Barmer to South Kala Amb project, worth almost ₹35,000 crore, up for bidding; OBD will be done on 1st April 2026.
Show source
So, we have projects like Bikaner, Barmer to South Kala Amb, which will cost almost ₹35,000 worth crore project, which is already up for bidding and OBD will be done on 1st April 2026.
- The company is discussing a 320 kV, 500 MW Paradeep to Andaman project that is likely to be commissioned by 2031 to 2032.
Show source
Then there is a discussion about 320 kV, 500 MW Paradeep to Andaman.
- The timeline for projects in the Brahmaputra basin, including Niglok in Arunachal Pradesh, Namsai, Roing, Silapathar, Gogamukh and Rauta, will vary depending on hydropower project progress; hydro projects take almost 8 to 10 years and HVDC projects almost four years, and the projects will be available for bidding depending on that progress.
Show source
So, these are some projects which are likely to be, in any are depending on the hydropower generation in Northeastern region, that the timeline will vary depending on the progress of hydro project, because hydro project time is almost, say, 8 to 10 years and HVDC project is almost four years.
- The Bikaner V to Begunia project is 6,000 MW and will be almost ₹35,000 crores.
Show source
Almost, it will be again ₹35,000 crores. - Mr. Sumeet Kishore – Axis Capital: - Thank you so much, sir. - Mr. Puneet – HSBC: - Thank you so much.
- HVDC TBCB project will spread its CapEx across the next 2 to 3 years; its HVDC RTM project given by the regulator will take about another 3 years, and the Bhadravati project will also be there over the next three years.
Show source
Those are the two projects over there which will be there in the next three years - the HVDC part and most of the TBCB projects, the general TBCB projects have a range of about 2 to 3 years of CapEx.
- Most of Power Grid Corporation of India Limited's remaining RTM projects have shorter durations and will overlap over about 18 months to 24 months.
Show source
They will also be overlapping in a similar period, about 18 months to 24 months, most of the projects. - Mr. Girish – Morgan Stanley: - And any comment on the market share for the new projects one in this fiscal year? - Mr. Burra Vamsi Rama Mohan – Director (Projects): - Yeah, we are having that guidance.
- POWERGRID has committed to the Government of India ₹37,000 crores for FY27 and ₹45,000 crores for FY28; major expenditure on its HVDC projects will occur during those periods.
Show source
We have already committed to Government of India for next financial year, FY27, ₹37000 crores and FY28, ₹45000 crores.
- POWERGRID is procuring bulk transformer packages, each with 30 transformers; one package can meet the requirements of two or three substations, and it may procure 10 to 12 such packages, with packages issued each year.
Show source
So , we are procuring as a bulk transformer a nd each package we are having 30 transformers, one package we are procuring which will be require ment for maybe 2 or 3, substations requirement will be taken in advance only in one package and such package, w e are maybe 10 to 12 package .
- POWERGRID said it would commission Bhadla-III to Sikar-II, Bhadla-III to Ramgarh, Navsari to Padghe, Maheshwaram to Kurnool, and Navsari to Kala in the remaining two months.
Show source
• Navsari to Kala. - These are the major elements which we will be commissioning. - These are the elements which have been commissioned since last quarter after 30 th September, 2025 –
- POWERGRID commissioned two ICTs at Fatehgarh III, one at Bhuj and one at Bhachau.
Show source
• Then 2 number ICTs at Fatehgarh III.
- POWERGRID procured a mobile GIS-mounted emergency restoration system for substations to restore electricity after a failure or disaster.
Show source
So, we have recently procured emergency restoration system for substation also.
- POWERGRID bid for the project based on its own cost, which differs from the NCT cost, and will ensure the project is executed within that limit.
Show source
But the cost considered by POWERGRID will be different from this cost and based on that cost only, we have bid out this project and we have won.
- The Bikaner V to Begunia project is expected to be approved shortly.
Show source
There are number of more projects like Bikaner V to Begunia, this should be shortly approved.
- Kurnool to Vishakhapatnam is one more project already discussed in NCT.
Show source
It is Kurnool to Vishakhapatnam. - Mr. Sumeet Kishore – Axis Capital: - Can two LCCs get awarded this year?
- The company expects Bhadla III to Sikar II, Bhadla III to Ramgarh, Navsari to Padghe, Kurnool III to Maheshwaram, Ananthapuram to Kadappa and Navsari to Kala to be commissioned and completed in Q4.
Show source
I can tell you the projects like we have Bhadla III to Sikar II, Bhadla III to Ramgarh, we have Navsari to Padghe, we have Kurnool III to Maheshwaram, we have Ananthapuram to Kadappa, we have Navsari to Kala, which are likely to be commissioned, completed in Q4.
- The company expects Koppal Gadag, Koppal to Raichur, Koppal to Narendra and Beawar Dausa in Q1; the projects will be commissioned in a phased manner.
Show source
Then, if we talk of Q1, we will have projects like Koppal Gadag, we will have Koppal to Raichur, we will have Koppal to Narendra, we will have Beawar Dausa.
- POWERGRID's major expenditure on its HVDC projects will happen after two years, when equipment starts coming to India for supply.
Show source
So , in after two years , the major expenditure will happen because all equipment will start coming to India and they will be supplied.
- POWERGRID is procuring transformers and reactors in advance for projects expected to come up for bidding and commissioning in two or three years, to avoid uncertainty over transformer availability.
Show source
Like suppose , I know that so many projects are coming for bidding and after two years or three years, so many transformers will be required for commissioning, so I should have those transformers in hand.
- POWERGRID's land acquisition cell becomes active when a project comes up for bidding and identifies three to four land options so land can be available immediately if POWERGRID wins the project.
Show source
3 to 4 option so that in case we win the project immediately, the land should be available.
- POWERGRID is mechanizing transmission-line tower erection with cranes, including central cranes.
Show source
So , it is now reality that cranes are to be used for, making transmission line towers or erecting transmission line towers.
- POWERGRID has used Portadeck mats for the last three to four years, allowing work in rainy and muddy conditions.
Show source
So, the Portadeck mats are being used in last 3 to 4 years.
- POWERGRID's Leh Pang RTM project is yet to be launched.
Show source
And one RTM project, which we are talking is the Leh Pang, which is yet to be launched basically.
- The HVDC project has a timeline of about four years and will be commissioned after three years. Replaced by a later filing.
Show source
So , after three years , it will be commissioned.
Demand and pricing
- Under the NEP guideline, there were almost 3 lakh crore of intra-state projects, of which only a few had been awarded so far.
Show source
Tyagi – Chairman & MD: - Like, there was, as per NEP guideline, there was a total three, almost 3 lakh crore projects under intra state.
- States such as Rajasthan are yet to award the balance intra-state projects, with projects worth almost ₹60,000 crores being discussed; Karnataka may have ₹60,000 to ₹70,000 crore, and other states with more renewable energy are expected to have projects too.
Show source
Similarly, Karnataka also, maybe ₹60,000 to ₹70,000 crore and other all states where renewable is more, so there will be number of projects, especially in intrastate and depending on the challenge, like if some project in Karnataka, like in Bangalore or in Maharashtra, like in Pune and Bombay.
- Intra-state projects are just opening up with states like Maharashtra and Karnataka.
Show source
Intrastate is just opening with states like Maharashtra and Karnataka opening up.
Segments
- POWERGRID is the largest company operating a 765 kV transmission network.
Show source
We are the largest company operating 765 kV transmi ssion network, which is the backbone of India's power sector. - In CapEx and capitalization and what elements we have recently commissioned .
- POWERGRID was born in 1989 and started operations in 1991-92.
Show source
So, like, POWERGRID is a company which was born in 1989 and we have started operations in 1991-92.
- POWERGRID has 18 HVDC stations.
Show source
Page 3 of 23 - These are the details of various voltage level substations.
- Hitachi, GE and Siemens are the three manufacturers of HVDC equipment. Replaced by a later filing.
Show source
Hitachi, GE and Siemens are there.
Deals and partners
- POWERGRID’s Kenya project is the first independent transmission project in Africa, with risk sharing with multilateral development partner Africa50, and estimated cost of about $311 million.
Show source
The estimated cost is about $311 million.
- POWERGRID entered into a partnership with Africa50 in Kenya.
Show source
We have entered into partnership with the Africa50 in Kenya, particularly.
- The company has given the Khavda Nagpur project, and Hitachi, GE and Siemens are executing the Fatehpur to Bhadla and Khavda to the South Olpad projects, all part of Adani.
Show source
So we have already given a project of this Khavda Nagpur and they are all also executing this Fatehpur to Bhadla project and then Khavda to the South Olpad, all part of Adani.
Risks, rules and outside factors
Outside factors
- Transformer manufacturers’ capacity is expected to reach 3,98,000 MVA in the next 2 to 3 years, compared with demand of 4,21,000 MVA in 26-27; Government of India relaxation allowing Chinese companies in India would boost the transmission sector.
Show source
And even if we consider their augmentation in next 2 to 3 years, the capacity become 3,98,000 MVA, whereas demand in 26-27 itself, it is 4,21,000 MVA.
- POWERGRID said there are supply chain constraints especially for transformers and reactors, and it is talking with IEEMA and Indian manufacturers about augmenting their manufacturing capacity.
Show source
• There are supply chain constraints especially for transformers and reactors.
- The company awards transmission contracts for transmission lines and substations on a firm-price basis, so metal prices will not impact returns on transmission line contracts; substation contracts have a PV clause considered during bidding, and the company does not expect much impact from commodity-price variations.
Show source
So, the metal prices are not goi ng to impact our returns in respect to the transmission line contracts.
Rules and policy
- POWERGRID expects right-of-way issues to be better resolved under Government of India guidelines issued in June 2024, March 2025 and December 2025, and said results are already seen on the ground as it is able to commission number of transmission projects.
Show source
So, with this guideline, we expect that RoW issues will be better to be resolved and results are already seen on the ground that we are able to commission number of transmission projects.
- Right-of-way area considered for compensation is 30% in rural areas, 45% in semi-urban areas and 60% in urban areas; land compensation is now based on market rate rather than circle rate multiplied by area, using a Government of India valuation methodology.
Show source
Now it is market rate.
- O&M charges for Power Grid Corporation of India Limited's regulated business have already been given for the next five years, and the next revision will be after 2029.
Show source
It's , they have already given the O&M charges for the next five years.
Show 2 more statements
Rules and policy
- Transformer manufacturing facilities of foreign countries available in India are likely to be approved by Government of India, which POWERGRID said will improve supply and reduce the problem.
Show source
They are also likely to be approved by Government of India.
- Government of India guidelines were subsequently adopted by the Government of Delhi, Government of Haryana, Government of Rajasthan and Government of Gujarat; district collectors or district magistrates issued orders for MRC rates or land rates in September and October, after which work started.
Show source
And finally, the orders for this MRC rate or land rate were issued by respective District Collector or Page 13 of 23 District Magistrate in September and October.
Everything else said on the call
What management stressed
- POWERGRID said its project execution and performance were improving in all areas, compared with the previous year when it faced challenges commissioning projects.
Show source
And now, our execution of projects, our performance is improving in all areas, unlik e last year wherein we had number of challenges in commissioning our projects.
- POWERGRID has set up a dedicated RoW cell at its corporate office, which monitors RoW matters day to day, and each region will have a RoW cell to discuss issues relating to each tower and transmission line.
Show source
So, the initiatives which we have taken in recent past, we have made dedicated RoW cell.
- The Government of India is helping POWERGRID resolve RoW issues, and POWERGRID is discussing such issues with state chief secretaries or the Government of India's Power Secretary when help is required on the ground.
Show source
So , Government of India is also helping POWERGRID in resolving RoW issues. - Second is, like transformers and reactors, w e are taking in advance.
- POWERGRID monitors project progress through cameras connected to control rooms in each region, enabling the Chairman to view project activity and discuss challenges with project managers.
Show source
But now project monitoring is also being done through control center installed by camera.
- POWERGRID wants to focus on critical renewable energy projects to prevent green power from being curtailed in India.
Show source
So, we want to focus on these projects so that no power is curtailed in India. - Mr. Shirom Kapoor – Jefferies: - Got it sir.
- POWERGRID is meeting chief ministers of various states, and the Power Minister is holding meetings with all the states. Replaced by a later filing.
Show source
And we are meeting with the chief ministers of various states.
Show 4 more statements
Other
- POWERGRID received an ‘Excellent’ MoU rating from the Government of India, Department of Public Enterprise, for 2024-25.
Show source
For 2024-25 again, like all the years, last so many years we have been achieving M oU rating of ‘Excellent’ by Government of India, Department of Public Enterprise. - As I told that gross fixed assets , for the first time it has crossed ₹3 lakh trillion.
- All TBCBs are under the new tax regime and are not paying MAT if there is no profit under the income tax rule; POWERGRID follows the old tax regime because it has 80(IA) benefits and will evaluate how long switching to the new tax regime would be beneficial.
Show source
So, we will have to evaluate that, how long it will be beneficial to switch over from old ta x regime to new tax regime for POWERGRID.
- Energy storage expansion will be about 47 GW by 2032; Pump Hydro Storage is about 36 GW, and clean energy commitments are more than 600 GW by 2032, with present capacity of 71 GW and additional electricity demand on account of Green Hydrogen production by 2032.
Show source
Then, 71 GW will be additional electricity demand only for Green hydrogen by 2032. - In Energy Stor age, we have 47 GW BESS, that is Battery Based Energy Storage, by 2032, and Pump hydro 27 GW.
- All other SPVs are under the new tax regime, and taxes paid by POWERGRID are pass through only.
Show source
And for POWERGRID, anyhow, whatever you pay the taxes, it is pass through only. - Mr. Apurva – IIFL: - So lastly, on the other also. - Mr. Bakul Gala – Moderator: - We have to restrict because there are others also.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
This transcript does not separate questions and answers, so they are not listed here.
Questions about this call
- When was the Power Grid Corporation of India Q3 FY26 earnings call transcript filed?
- Power Grid Corporation of India filed the transcript with the exchange on 9 Feb 2026. This page is built from that transcript.
- What does this page list?
- 139 statements from the transcript across 12 topics, 100 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- No. This transcript does not separate the questions from the answers, so they are not listed. The statements by topic still cover what management said.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.