Power Grid Corporation of India Q1 FY26 earnings call: POWERGRID received 58 Crore worth of orders in its telecom business
By DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person.
Transcript filed .
POWERGRID received 58 Crore worth of orders in its telecom business. POWERGRID has a target of about ₹28,000 Crore of CAPEX and commissioning of about ₹22,000 Crore. POWERGRID commissioned its Dausa 765 kV/400 kV substation in July’25, about 8 months after its foundation stone was laid in December’24; the commissioning time was a record. POWERGRID's system availability is 99.84%. POWERGRID has about 101GW of inter-regional capacity out of total inter-regional capacity of 120GW.
The numbers management gave
Results
- POWERGRID's system availability is 99.84%.
Show source
Our system availability is 99.84%.
- POWERGRID's CAPEX in Q1 FY 2025-26 was ₹6,981 Crore, compared with ₹4,615 Crore last year.
Show source
• If you see here CAPEX, we have CAPEX in Q1FY26, ₹6,981 Crore as compared to ₹4,615 Crore last year.
- POWERGRID commissioned ₹2,800 Crore in Q1 FY 2025-26, compared with about ₹2,400 Crore last year.
Show source
• In commissioning, we have done already commissioning of ₹2,800 Crore as against about ₹2,400 Crore last year.
- POWERGRID has maintained transmission system availability above 99.75%; availability was 99.82% last year and 99.84% so far in Q1 FY 2025-26.
Show source
Last year it was 99.82% and so far, we have 99.84%, which is one of the best availability or transmission system availability in the world.
- POWERGRID maintained 0.27 trippings per line last year, equivalent to 1 line trip in almost 4 years.
Show source
Tripping per line, we have maintained last year 0.27.
- POWERGRID's Q1 FY 2025-26 total income was ₹11,444 Crore, EBITDA was ₹9,527 Crore and Profit After Tax was ₹3,631 Crore; on a standalone basis, income was ₹11,257 Crore, EBITDA was ₹9,623 Crore and Profit After Tax was ₹3,653 Crore.
Show source
Transmission charges, consultancy services, telecom, other income put together, it is 11,444 Crore, EBITDA 9,527 Crore and Profit After Tax as shown earlier, 3,631 Crore. - On standalone basis, income is ₹11,257 Crore and EBITDA ₹9,623 Crore, Profit After Tax is 3,653 Crore. - If we see other financial parameters, the Gross Fixed Assets are about ₹2,92,000 Crore, Capital work in progress including advance is about ₹41,000 Crore, we have debt of about ₹1,30,000 Crore, Net Worth of about ₹96,000 Crore, Earnings per share ₹3.9 for Q1.
Show 17 more statements
Results
- POWERGRID's net worth was about ₹96,000 Crore, Gross Fixed Assets were about ₹2,92,000 Crore, capital work in progress including advance was about ₹41,000 Crore and debt was about ₹1,30,000 Crore in Q1 FY 2025-26.
Show source
Transmission charges, consultancy services, telecom, other income put together, it is 11,444 Crore, EBITDA 9,527 Crore and Profit After Tax as shown earlier, 3,631 Crore. - On standalone basis, income is ₹11,257 Crore and EBITDA ₹9,623 Crore, Profit After Tax is 3,653 Crore. - If we see other financial parameters, the Gross Fixed Assets are about ₹2,92,000 Crore, Capital work in progress including advance is about ₹41,000 Crore, we have debt of about ₹1,30,000 Crore, Net Worth of about ₹96,000 Crore, Earnings per share ₹3.9 for Q1.
- POWERGRID's debt/equity ratio was 58:42 in Q1 FY 2025-26, representing 58% loan and 42% equity.
Show source
• Our Debt Equity is 58:42 - 58% loan and 42% equity. - These are financial parameters.
- POWERGRID's earnings per share was ₹3.9 for Q1 FY 2025-26, and its book value per share was ₹103 per share.
Show source
Transmission charges, consultancy services, telecom, other income put together, it is 11,444 Crore, EBITDA 9,527 Crore and Profit After Tax as shown earlier, 3,631 Crore. - On standalone basis, income is ₹11,257 Crore and EBITDA ₹9,623 Crore, Profit After Tax is 3,653 Crore. - If we see other financial parameters, the Gross Fixed Assets are about ₹2,92,000 Crore, Capital work in progress including advance is about ₹41,000 Crore, we have debt of about ₹1,30,000 Crore, Net Worth of about ₹96,000 Crore, Earnings per share ₹3.9 for Q1.
- POWERGRID's return on net worth was 3.76% for Q1 FY 2025-26.
Show source
Return on Net Worth is 3.76% for Q1. - Other financial parameters.
- POWERGRID's Q1 FY 2025-26 billing was ₹8,434 Crore, realization was ₹8,671 Crore and outstanding was ₹3,151 Crore, compared with ₹5,548 Crore in Q1 of last year.
Show source
Billing is ₹8,434 Crore, Realization ₹8,671 Crore, Outstanding in Q1 is ₹3,151 Crore against ₹5,548 Crore Q1 of last year. - In other business, telecom and consultancy:
- POWERGRID's telecom income increased from ₹246 Crore to ₹289 Crore in Q1 FY 2025-26.
Show source
• Income from telecom has increased from ₹246 Crore to ₹289 Crore.
- POWERGRID's telecom business added 16 customers.
Show source
Customers added 16 numbers.
- POWERGRID's consultancy income was ₹329 Crore in Q1 FY 2025-26, including about ₹153 Crore revenue from new business of smart meters in FY25-26.
Show source
• In consultancy, our income is ₹329 Crore in Q1 which includes new business of smart meters, which we got revenue in FY25-26 of about ₹153 Crore.
- POWERGRID's capitalization was about ₹1,800 Crore in Q1 FY 2025-26.
Show source
So, our capitalization is about ₹1,800 Crore. - Analyst: - This was Q1? - Mr. R.K.
- POWERGRID said that after a loan period of 10 or 12 years, the loan component is almost over, reducing loan interest that is passed through and received as revenue.
Show source
So, interest on loan and that component also reduces.
- POWERGRID's standalone profit increased by about 7% in Q1 FY 2025-26.
Show source
Tyagi – Chairman & Managing Director - 7%.
- POWERGRID's consolidated profit declined mainly because Q1 FY 2025-26 CSR expenditure was about ₹70 Crore higher than last year and its loss from EESL or its joint venture company was higher.
Show source
And main reason for this is, our expenditure in CSR is about ₹70 Crore more as compared to last year in Q1.
- POWERGRID had standalone profit of ₹3,653 Crore and subsidiary profit of ₹364 Crore in Q1 FY 2025-26; a ₹342 Crore dividend to POWERGRID was eliminated, leaving only about ₹20 Crore growth in consolidated profit, which was reduced by joint venture losses.
Show source
So, actually we are left with only some ₹20 Crore growth in the consolidated, but because of the JV loss it is coming down. - Mr. Sumit Kishore – Axis Capital: - Got it.
- Consolidated operating expenses increased from ₹1,462 Crore to ₹1,873 Crore in Q1 FY 2025-26, about 28%, partly because ₹135 Crore of smart metering expenditure in Gujarat was included in other expenditure, along with ₹79 Crore of additional CSR compared with Q1 and other R&M expenditures; FERV also contributed net movement.
Show source
While we are happy to look at on an annual basis, but if you look at this latest quarter, your operating expenses on a consolidated basis, moved from ₹1,462 Crore to ₹1,873 Crore, about 28% growth.
- POWERGRID's Telecom segment had 100% backbone availability in financial year 2024-25.
Show source
Backbone availability has been 100% as always.
Money and capital
- POWERGRID's capex was about ₹28,000 Crore, of which almost ₹6,700 Crore had already been incurred, and about ₹21,000 crore of capex would be added.
Show source
And moreover, we will have Capex of about ₹28,000 Crore, out of which almost ₹6,700 Crore capex is already done.
- The company normally invests 20% equity in TBCB projects; that would require ₹7,000 to ₹8,000 Crore of equity per year over three years, against expected profit of about ₹16,000 Crore, which it can manage from internal resources and market borrowing at 6.9% or 6.95%.
Show source
So, 20% equity means if we divide it by 3 years, so every year we will have say ₹7,000 to ₹8,000 Crore equity.
What it expects ahead
What management expects
- POWERGRID has a target of about ₹28,000 Crore of CAPEX and commissioning of about ₹22,000 Crore.
Show source
• We have target of about ₹28,000 Crore of CAPEX and commissioning of about ₹22,000 Crore.
- POWERGRID has a commissioning target of ₹3,000 Crore in Q2, about ₹7,000 Crore in Q3 and about ₹8,000 Crore in Q4, totaling around ₹22,000 Crore.
Show source
• Q2, we have ₹3,000 Crore worth commissioning target, Q3 about ₹7,000 and Q4 about ₹8,000 Crore.
- POWERGRID's CAPEX plan is ₹28,000 Crore, including about ₹3,500 Crore of RTM, about ₹19,000 Crore of TBCB and ₹5,300 Crore of other projects.
Show source
So, put together we have projects in hand about ₹1,48,000 Crore. - Our Capex plan is ₹28,000 Crore and which includes RTM of about ₹3,500 Crore, TBCB about ₹19,000 Crore and other projects ₹5,300 Crore.
- POWERGRID's CAPEX plan is about ₹35,000 Crore in FY27 and about ₹45,000 Crore in FY28.
Show source
Next year, about FY27, we will have CAPEX plan of about ₹35,000 Crore and in one year after next year, that means FY28, will be about ₹45,000 Crore.
- POWERGRID is likely to participate in a Rajasthan tender for about 2000 MW/ 4000 MWh of BESS.
Show source
So, we are likely to participate in that project.
- POWERGRID wants to develop as a big player in BESS and Green Hydrogen in the next 2-3 years.
Show source
So, in next 2-3 years, we want to develop as a big player in these areas. - Analyst: - Thank you very much for your detailed thoughts, sir and all the best to the entire team.
Show 16 more statements
What management expects
- POWERGRID said ₹22,000 Crore worth of projects from its ₹38,000 Crore work in progress were going to be commissioned this year.
Show source
So now if we are saying, out of ₹38,000 Crore work in progress, so ₹22,000 Crore worth projects are going to be commissioned this year.
- POWERGRID expected capitalization of ₹20,000-₹25,000 Crore in the next financial year, maybe about ₹25,000 Crore.
Show source
So again, there will be ₹20,000-₹25,000 Crore worth capitalization in next financial year also, maybe about ₹25,000 Crore. - Analyst: - Okay.
- POWERGRID said annual revenue from RTM projects is reducing and is compensated by revenue from TBCB projects; without commissioning more than ₹20,000 Crore of TBCB projects, revenue would be almost constant or could reduce.
Show source
Otherwise, if we are not able to commission more than ₹20,000 Crore projects in TBCB, our revenue model, it will be almost constant or sometimes it may reduce also. - Analyst: - Fair enough, sir.
- POWERGRID expected the ₹67,000 Crore projects, including projects in Uttar Pradesh such as Roberts Ganj, Vindhyachal and Prayagraj, to be finalized within this financial year.
Show source
There are some major projects in UP like Roberts Ganj, Vindhyachal and Prayagraj, like that, number of projects are there, and more projects are likely to be….. all ₹67,000 Crore project I think, it will be finalized within this financial year. - Mr. Sumit Kishore – Axis Capital: - So, this South Olpad will be a VSC HVDC project?
- The company expects about 85% of commissioning to be TBCB and 15% RTM; in 2025 -2026, major RTM projects include Navsari, Padghe, and Kurnool, Maheshwaram, and the following year commissioning will be almost 90% TBCB and maybe 10% RTM.
Show source
Tyagi – Chairman & Managing Director - We don't have many RTM projects, so maybe I can say in percentage only, maybe about 85% TBCB and 15% of RTM.
Orders
- POWERGRID received 58 Crore worth of orders in its telecom business.
Show source
We have received 58 Crore worth orders.
- About ₹29,000 Crore worth of new projects had been approved and were yet to be floated, with bids yet to come.
Show source
So, we are not seeing any decline in this area whereas as far as new projects, about ₹29,000 Crore worth projects are approved which are yet to be floated, bids are yet to come.
- About ₹39,000 Crore worth of projects had been bid out and were due for bid submission or e-RA.
Show source
And about ₹39,000 Crore worth projects are already bid out and which are due for submission of the bid or due for e-RA.
- About ₹67,000 Crore worth of projects were up for winning, and POWERGRID could win maybe 50% or 60% of them.
Show source
So put together, we have about ₹67,000 Crore worth projects which are basically for winning or we can win maybe 50% or 60% of those.
- About ₹75,000 Crore worth of projects had recently been approved in NCT and would be taken up for bidding in future.
Show source
Apart from this, there are about ₹75,000 Crore worth projects which have been recently approved in NCT, which will be taken up for bidding in future.
- About ₹1,40,000 Crore worth of projects were up for grab.
Show source
So maybe put together, if we see that ₹1,40,000 Crore worth projects are up for grab.
- ₹39,000 Crore of projects were already up for grab.
Show source
₹39,000 Crore are already up for grab.
- POWERGRID had participated in the Khavda III to South Olpad HVDC project, with an NCT cost of about ₹12,000 Crore and an estimated actual project cost of ₹18,000-₹20,000 Crore.
Show source
And we have already participated like in HVDC from Khavda III to South Olpad, which is having NCT cost of about ₹12,000 Crore and whereas actual project cost may be around ₹18,000-₹20,000 Crore.
- POWERGRID had submitted its bid for Khavda KPS 3 to South Olpad, and e-RA was expected to take place anytime.
Show source
It is already, bid is already submitted, and it will be anytime, e-RA will be done.
- The company targets a project cost of about ₹99,000 Crore for its TBCB work in hand, unless there is force majeure or a change in law; compensation for land ordered by the government after the project is won would be covered under change in law and would be additional.
Show source
Tyagi – Chairman & Managing Director - Work in hand we have say ₹99,000 Crore almost. - Mr. Girish - Morgan Stanley: - Yeah.
- POWERGRID won its first TBCB HVDC project from Khavda to Nagpur, with about 6,000 MW capacity, to transmit power from Khavda to Nagpur and then to Maharashtra and other parts of the country.
Show source
Again, it is 6,000MW project.
What it is building and selling
Projects and capacity
- POWERGRID commissioned its Dausa 765 kV/400 kV substation in July’25, about 8 months after its foundation stone was laid in December’24; the commissioning time was a record.
Show source
The foundation stone was laid by me in December’24 and it was commissioned in July’25.
- POWERGRID's Namsai - Kathalguri transmission line under TBCB was commissioned in May’25, 5 months before its October’25 target schedule.
Show source
Target schedule was October’25 whereas it has been commissioned in May’25.
- POWERGRID commissioned its first international ILD link, with 10G capacity.
Show source
First international ILD link of 10G capacity has been commissioned.
- The Leh and Ladakh project had been delayed because it is challenging to execute at a height of 4,500 metres to 5,000 metres, and only one party was interested in executing it and had apprehensions.
Show source
Okay, as far as Leh and Ladakh project is there, that yes, there has been delay because it is a very challenging project and only one party is now interested to execute this project which is also having some apprehension because it is a very challenging project working at height of 4,500 metres to 5,000 metres.
- POWERGRID had commissioned projects worth about ₹2,800 Crore by July.
Show source
Tyagi – Chairman & Managing Director - Yes, we have mentioned commissioning of about ₹2,800 Crore.
- At Khavda-II, two transformers were commissioned and carrying power for evacuation from 400 kV generation to 765kV Lakadia, but POWERGRID could not capitalize the project because two transformers remained uncommissioned.
Show source
So, two transformers are already commissioned, power flow is there through that, evacuation from 400 kV generation to 765kV, Lakadia is already happening but since we have not commissioned two numbers of transformers, so we are not able to capitalize that.
Show 24 more statements
Projects and capacity
- POWERGRID had approved the Barmer to South Kalamb conventional LCC-based HVDC project; it was approved in NCT and expected to come for bidding in another 2-3 months.
Show source
And it is already approved in NCT and may be another 2, 3 months, it will come for bidding.
- POWERGRID expected commissioning of the Bikaner V to Begunia HVDC project in 2029-30.
Show source
And it is expected commissioning is about 2029-30.
- The South Kalamb to Barmer project's NCT cost was ₹24,000 Crore, while its actual execution cost was expected to be around ₹28,000-₹30,000 Crore.
Show source
But actual project execution cost will be around ₹28,000-₹30,000 Crore. - Mr. Sumit Kishore – Axis Capital: - Thank you so much. - Mr. G. Ravisankar - Director (Finance) & CFO - Sumit, to be precise to your question like we have a standalone profit of ₹3,653 Crore and we have a profit of ₹364 Crore in subsidiaries but again in Q1 we took a dividend of ₹342 Crore to POWERGRID.
- The company procures transformers and major components well in advance, even before a project is in hand; it procures 30 transformers in one package, enough for 2-3 projects when a project may require 6 or 9 transformers.
Show source
Page 18 of 22 Like we are procuring 30 transformers in one package and maybe one project may be having say 6 transformers or 9 transformers.
- POWERGRID commissioned its Khavda-II and Khavda-III stations, which were required to evacuate RE power from the Khavda region.
Show source
So, both have been commissioned now.
- POWERGRID commissioned Kurnool III for RE power.
Show source
• Then Kurnool III is also commissioned, which is also for RE power.
- POWERGRID placed an order for Green Hydrogen at its Neemrana substation, where it will generate Green Hydrogen using solar panels or a solar plant installed at the station; the Green Hydrogen may be used in gas form for various applications or to generate electricity back to the grid.
Show source
As regards to Green Hydrogen and BESS , we have already placed order for Green Hydrogen in our Neemrana substation where we will generate Green Hydrogen by solar panels or solar plant installed in the station itself.
- Transmission lines being planned and executed by POWERGRID or other transmission system developers are outside the GIB area, and the GIB issue is no longer affecting transmission lines.
Show source
Tyagi – Chairman & Managing Director - It is no longer an issue now.
- The sole bidder for the Leh and Ladakh project had submitted its bid, which was under evaluation; queries were being addressed and were likely to be resolved in maybe another two months.
Show source
But nevertheless, they have already submitted their bid which is under evaluation.
- After the queries are resolved, POWERGRID is considering awarding the Leh and Ladakh project to that particular HVDC OEM.
Show source
After that, we are considering awarding the project to that particular HVDC OEM.
- POWERGRID is also exploring whether an AC transmission network is feasible for the Leh and Ladakh project if HVDC cannot be achieved.
Show source
Page 10 of 22 Parallelly, we are also considering, suppose we are not able to achieve this HVDC, so parallelly we are also exploring possibility whether AC transmission network is feasible or not.
- POWERGRID said VSC-based HVDC is the most suitable technology for evacuating power from Leh to Kaithal because there is no generation or grid connectivity and the transmission network and power system are very weak.
Show source
In that condition, HVDC, VSC based HVDC is the best solution.
- POWERGRID said that if it cannot mature or finalize VSC-based HVDC technology for Leh to Kaithal, an AC network would require dynamic compensation, synchronous condensers and STATCOMs, adding to the cost; synchronous condensers have not been used in India so far.
Show source
But suppose we are not able to mature that technology or we are not able to finalize the VSC based HVDC system, then AC network will require number of dynamic compensation, synchronous condenser, STATCOMs.
- POWERGRID said it capitalizes a project when all its elements are commissioned; one Khavda-II to Khavda-III circuit remained uncommissioned and was likely to be commissioned very shortly, after which the project would be capitalized.
Show source
So, all elements are commissioned except one circuit of Khavda-II to Khavda-III elements, which is likely to be commissioned very shortly.
- POWERGRID identified the India - Sri Lanka HVDC project, Paradeep to Andaman, and Imphal to Myanmar Back to Back HVDC project as visible pipeline projects.
Show source
So as of now these are visible whereas there are number of more projects but visibility is for these projects. - Mr. Sumit Kishore – Axis Capital: - For the next 2, 3 years. - Mr. R.K.
- POWERGRID said inter-country HVDC projects, including projects involving Saudi Arabia, Oman or UAE, would use VSC technology because they involve very long distances.
Show source
So, it is going to be VSC only. - Mr. Sumit Kishore – Axis Capital: - Just final thing, what would be the rough project cost you think that could be there for the South Kalamb project?
Segments
- POWERGRID has about 101GW of inter-regional capacity out of total inter-regional capacity of 120GW.
Show source
Inter- regional capacity, we have about 101GW out of total 120GW inter-regional capacity.
- POWERGRID's 101GW inter-regional capacity represents about 84% of the total inter-regional capacity.
Show source
Since day one, We are operating about 84%, which is 101GW.
- POWERGRID's transmission asset base comprises about 1,80,000 circuit kilometer, 1,500 transmission lines, 5,71,000 MVA transformation capacity and 286 substations.
Show source
And now RE power mainly concentrated in Rajasthan and Gujarat can be transmitted in north-eastern region or in southern region. - Our domestic and international credit rating is very good, it is at par with the sovereign rating. - We have 5 functional directors - 2 Government Nominee Directors, 3 Independent Directors including one-woman Independent Director, Smt. Sajal Jha. - We have a huge transmission asset base, about 1,80,000 circuit kilometer, 1,500 transmission lines, 5,71,000 MVA, transformation capacity and 286 substations.
- POWERGRID has 18 HVDC stations.
Show source
We have large number of HVDC station s, 18 numbers, which is one of the highest in the world.
- POWERGRID has 69 765 kV stations, the largest number in the world by any country.
Show source
As far as 765 kV stations are there, it is largest in the world by any country, 69 numbers.
- POWERGRID has 199 substations at 400 kV and below.
Show source
We have 199, 400 kV and below substations.
- POWERGRID has 20 STATCOMs and SVCs and 67 GIS.
Show source
Then for grid reliability and stability, we have 20 STATCOMs and SVCs, 67 numbers of GIS.
- POWERGRID's intra-city telecom network is present in 500 cities.
Show source
Intra-city network is there in 500 cities.
Risks, rules and outside factors
Outside factors
- For TBCB or RTM projects, supply cost is about 50% of total cost, civil and erection cost is about 30% to 35%, and RoW cost is about 15% to 20%; supply costs are increasing because demand is higher, with normal inflation of 5% to 6%, possibly 7% to 8%, and transformer cost increasing by 10% to 20%.
Show source
So, it is varying from 10% to 20%.
- A transformer that cost about ₹14 Crore seven years ago costs almost ₹30 Crore now, and a GIS bay that cost about ₹6 crore per bay now costs about ₹14 to ₹15 Crore per bay.
Show source
So, where GIS bay, suppose which was about ₹6 crore per bay, now cost is about ₹14 to ₹15 Crore per bay.
Rules and policy
- In 2024 June, guidelines set land compensation for right of way for farmers at 15% to 30%, and compensation for the land between a tower's four legs at 85% to 200%, at circle rate.
Show source
In 2024 June, we were able to issue guidelines for farmers that from 15% to 30% land compensation for RoW.
- In March 2025, Government of India issued guidelines replacing circle rate with market rate for compensation, as farmers were not agreeing to circle rate and market rate may be almost four times to six times the circle rate.
Show source
So, Government of India has now issued guidelines for paying compensation as per the market rate.
- Karnataka has a ₹250 Crore threshold, Maharashtra ₹500 Crore, and MP ₹250 Crore; projects above these thresholds will be under TBCB, creating opportunities in these states.
Show source
That means above this threshold level, all the projects will be under TBCB.
Everything else said on the call
Other
- POWERGRID has been successful in resolving right-of-way issues in Maharashtra and Gujarat, and to some extent in Rajasthan; it is resolving issues in Delhi and Haryana, where issues remain unresolved.
Show source
We are very successful in resolving issues in Maharashtra, Gujarat and to some extent in Rajasthan.
- POWERGRID said right-of-way conditions were better this year than last year, but a lot remained to be done. Replaced by a later filing.
Show source
Tyagi – Chairman & Managing Director - If you compare last year and this year, yes, it is better but there is a lot required to be done.
What the company said on its earnings call, taken from its own transcript. Not advice.
Questions and answers
This transcript does not separate questions and answers, so they are not listed here.
Questions about this call
- When was the Power Grid Corporation of India Q1 FY26 earnings call transcript filed?
- Power Grid Corporation of India filed the transcript with the exchange on 8 Aug 2025. This page is built from that transcript.
- What does this page list?
- 82 statements from the transcript across 9 topics, 68 of them with a figure. Each statement is shown with the transcript sentence it came from.
- Are the analysts' questions included?
- No. This transcript does not separate the questions from the answers, so they are not listed. The statements by topic still cover what management said.
- Who wrote this page?
- DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.