Acme Solar Holdings Q4 FY25 earnings call: ACME Solar Holdings Limited's CUF is bound to go up as it captures the full-year impact of the 1200 megawatt project next year

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

ACME Solar Holdings Limited's CUF is bound to go up as it captures the full-year impact of the 1200 megawatt project next year. The PPA for 190 megawatts of a 380 megawatts project was signed in June of last year, and the project's scheduled COD is June of next year, with 2 years' time to execute. ACME Solar Holdings Limited's newly commissioned 1200 megawatt project in Fatehgarh, Rajasthan, recorded 32% CUF in the last quarter. The company expects tariffs for the remaining pure solar tenders to be between 2.7 and 2.8, given interest rates and integrated facilities. More than 60%-70% of ACME Solar Holdings Limited's operational capacity is connected to the central grid, allowing the company to potentially play the merchant market on the battery side if it can execute faster.

The numbers management gave

Results

  • ACME Solar Holdings Limited's newly commissioned 1200 megawatt project in Fatehgarh, Rajasthan, recorded 32% CUF in the last quarter.
    Show source
    So, in terms of the capacity utilization factor for this new project which we have commissioned, we did more than 30% CUF, 32% to be exact in the last quarter.
  • Operationalization of ACME Solar Holdings Limited's 1200 megawatt project in Fatehgarh, Rajasthan, helped bring the company's CUF up to 25.6% in Q4 & FY'25.
    Show source
    Of course, you are right that operationalization of this 1200 megawatt project in Rajasthan and that too in the highest sunlight zone of Rajasthan, which is Fatehgarh, which has helped us get the CUF up to 25.6%2.
  • ACME Solar Holdings Limited's Rajasthan portfolio recorded around 29.4% CUF on an annualized basis in Q4 & FY'25.
    Show source
    And as you mentioned, Rajasthan as a state, if you look at our portfolio there, which is very large, that has done around 29.4% CUF on an annualized basis.
  • The company increases CUF by sharing AC infrastructure with larger DC infrastructure and putting around 1.5 times more modules on each inverter; this makes sense given the cost benefit of installing more modules over the same AC infrastructure.
    Show source
    We have been doing higher CUF, because in terms of the sharing the AC infrastructure with the larger DC infrastructure by putting more modules of around 1.5 times overloading on each inverter.
  • ACME Solar Holdings Limited expected to sign PPAs for 400 to 500 megawatt last quarter, but the signing shifted to this quarter.
    Show source
    I think PPA signing, we were expecting to sign 400 to 500 megawatt last quarter, but unfortunately it shifted to this quarter.

Money and capital

  • ACME Solar Holdings Limited's net operational debt to EBITDA was 4.4 as of FY '25, within its guided range of 5.5.
    Show source
    As of FY '25, our net operational debt to EBITDA stands at 4.4, which is well within our guided range of 5.5.
Show 9 more statements

Money and capital

  • ACME Solar Holdings Limited's net debt to net worth ratio improved to 1.7x during FY '25.
    Show source
    Our net debt to net worth ratio has improved to 1.7x, reflecting continued progress in our financial discipline.
  • ACME Solar Holdings Limited expanded its asset base by around INR4,100 crores during FY '25, bringing its total gross block to around INR15,500 crores.
    Show source
    During the year, we expanded our asset base by around INR4,100 crores, bringing the total gross block to around INR15,500 crores.
  • ACME Solar Holdings Limited had cash and bank balances of around INR2,900 crores as of FY '25.
    Show source
    We continue to maintain a robust liquidity position with cash and bank balances of around INR2,900 crores as of FY '25.
  • The projects were financially closed before the last quarter ended and were part of INR16,500 crores mentioned in this quarter and last quarter.
    Show source
    And they closed, I think, the INR16,500 crores we mentioned in this quarter and last quarter, they were part of that.
  • ACME Solar Holdings Limited's battery capex is much below the budget in its initial bid budget and prevailing prices at the time of the bid; the suppliers are tier 1 suppliers.
    Show source
    But what I can tell you is that it is definitely much below the budget we had in terms of the initial bid budget.
  • The company refinanced one 300 megawatt ISTS project out of the 1200 megawatt recently commissioned and received a double AA- rating for it.
    Show source
    And that got us a rating of double AA-.
  • The company is typically getting 8.5% to 8.6% when borrowing at that credit rating.
    Show source
    So, right now, if we borrow, we are typically getting 8.5% to 8.6% at that credit rating.
  • The company has taken long-term financings for 20 years, rather than short-term 5 year or 7 year financing, to allow free cash flow to equity for capex and improve project return ratios.
    Show source
    These are all long term financings we have taken for 20 years, which allows us to get free cash flow to equity, which we need to do capex and which allows us to improve the return ratios of the project also.
  • The company will supplement INR16,5003 crores of debt with around INR4,000 crores of equity to fund INR20,000 crores of capex.
    Show source
    So, you can say the INR16,5003 crores of debt will be supplemented by around INR4,000 crores of equity, and that will help us do INR20,000 crores of capex.

What it expects ahead

What management expects

  • ACME Solar Holdings Limited's CUF is bound to go up as it captures the full-year impact of the 1200 megawatt project next year.
    Show source
    So, as we move forward and we capture the full year impact of this project next year, the CUF is bound to go up.
  • Expected CUF for FDRE projects in a 40% bid will be around 43% to 45%.
    Show source
    So, you can say in a 40% bid, it will be around 43% to 45%.
  • Expected CUF for FDRE projects in a 50% bid will be around 50% to 55%.
    Show source
    In a 50% bid, it will be around 50% to 55%.
  • Expected CUF for hybrid projects will be more than 30%, maybe around 35%, 40%.
    Show source
    And of course, on a hybrid, it will be around more than 30%, maybe around 35%, 40%.
  • The company expects all of the recently commissioned 1200 megawatt to receive a good rating in a similar band to the earlier project’s rating.
    Show source
    So, we are expecting that all of this 1200 megawatt should get a good rating in the similar band, which the earlier project has got.
  • The company expects borrowing costs to reduce depending on base rates, and says improved credit ratings allow it to get the best-in-class rate for an operational asset, around 8.5% today for a AA asset.
    Show source
    And of course, the improvement in credit rating allows us to get the best in class rate for an operational asset, which is around 8.5% today for a AA asset.
Show 8 more statements

What management expects

  • The company will not raise further equity to fund capex and will schedule capex prudently as per available resources, bid conservatively, and stagger PPAs and commissioning to reach 10 gigawatts on a more balanced yearly basis; new project profiles are coming with storage, with less wind capacity and more solar and battery, reducing capex per bid.
    Show source
    But still, we will try and basically stagger our PPAs and stagger our commissioning timeline such that we reach 10 gigawatts, but we reach in a way which is yearly-wise more balanced and concentrated in a particular year.
  • The company is trying to reach 7 gigawatts of contracted capacity.
    Show source
    But in terms of contracted capacity, which determines your revenue and CUF, this is 7 gigawatts is what we are trying to reach.
  • 10 gigawatt target is a combination of FDRE and hybrid and would represent more than 20 gigawatts of installed capacity.
    Show source
    And as we move forward, this 10 gigawatt again is a combination of FDRE and hybrid.
  • Battery has become an integral part of all ACME Solar Holdings Limited projects that will come up in future.
    Show source
    We are also seeing that the battery has become an integral part of all our projects which will come up in future.
  • FDRE and hybrid projects will have higher revenue per megawatt of contracted capacity and higher capex per megawatt of contracted capacity, with favorable return ratios.
    Show source
    So, that will give a higher revenue per megawatt of contracted capacity.
  • The company has not projected the reduction in borrowing costs, but it is likely to get some benefit from new refinancing if rates fall; refinancing already disbursed is locked in for a year, while sanctions dependent on the base rate may benefit depending on disbursement timing.
    Show source
    We are not really projecting it, but of course, it is likely to happen that in terms of the, if the rates fall, we are likely to get some benefit of the new refinancing.
  • The company will not invest in PSP until it gets a tariff in sync with the construction risk of a PSP.
    Show source
    But we will not do capex until we get a good tariff, which is in sync with the construction risk of a PSP.
  • Borrowing cost is expected to improve as rates fall. Replaced by a later filing.
    Show source
    Of course, it is expected to improve as the rates fall, which is again a macroeconomic thing.

What it is building and selling

Projects and capacity

  • The PPA for 190 megawatts of a 380 megawatts project was signed in June of last year, and the project's scheduled COD is June of next year, with 2 years' time to execute.
    Show source
    So, in terms of timelines for this project, the PPA got signed for 190 megawatts of the 380 megawatts in June of last year.
  • The PPA timeline for SJVN's 320 and 250 megawatt projects, around 5701 megawatts, is May 2026.
    Show source
    And similarly, for the 320 Page 6 of 21 ACME Solar Holdings Limited May 20, 2025 and 250 megawatt, that's around 5701 megawatts of SJVN, that's also the timeline is May 2026 as per the PPA.
  • The company is adding 450 megawatt on an AC basis, or around 600 megawatt peak on a DC basis, in FY '26.
    Show source
    450 megawatt is what we are adding in this year.
  • The company expects to add around 2.2 gigawatts in FY '27 as per signed PPAs.
    Show source
    In terms of the FY '27, bulk of our capacity is coming up in FY '27, which is as per the signed PPAs, which we just mentioned around 2.2 gigawatts, right?
  • The company expects 1.89 gigawatt in FY '27; capacity for which PPAs have not been signed is expected beyond FY '27, although construction has begun, and the company will not incur capex until a PPA is signed.
    Show source
    Nikhil Dhingra: 1.89 gigawatt in FY '27.
  • The company has blocked connectivity that allows it to commission before FY '27, and can commission after FY '27 with a 2-year grace period after PPA signing; roughly around 2 gigawatts of the rest of the capacity is beyond FY '27.
    Show source
    Page 11 of 21 ACME Solar Holdings Limited May 20, 2025 Ankit Verma: It's roughly around 2 gigawatts.
Show 18 more statements

Projects and capacity

  • The company is targeting the later part of Q2 for execution of its 200 megawatts pilot project at operational sites, and Q3 for large-scale BESS projects, subject to components and approvals.
    Show source
    So, that we are targeting for Q2, the later part of Q2.
  • The storage project has a capacity of 600 megawatt for 6 hours, or 6 megawatt hours of storage.
    Show source
    Nikhil Dhingra: It's a 600 into 6 megawatt hour of storage, 6 hours of storage.
  • ACME Solar Holdings Limited planned a 300 megawatt Sikar solar plant.
    Show source
    Second area is I think we wanted to do our Sikar 300 megawatt solar plant.
  • ACME Solar Holdings Limited has financing and land for the assets for which PPAs are signed, is ordering GIS, transmission line, transformers and batteries, and has started construction and the transmission line for these projects.
    Show source
    We have started construction.
  • ACME Solar Holdings Limited has tried to prepone the battery side, which can leverage its already operational substations and associated infrastructure.
    Show source
    We have also tried and preponed the battery side which of course can leverage the already operational substations we have with all the associated infrastructure.
  • First FDRE schedule date is May and June, and it will try to commission sooner where the substation is ready on a short-term open access basis by building the plant and transmission line; operating on STO does not give a binding commitment to evacuate and means a slightly lower realization of capacity.
    Show source
    But what we'll try, wherever the substation is ready on a short-term open access basis, we'll try and commission it sooner by building the plant and the transmission line and every other thing.
  • The company can install batteries at an already operational substation and use its infrastructure, selling the power on a merchant basis until it plugs the battery into a PPA.
    Show source
    So, what you can do till the time you plug into a PPA, you can install the batteries on an already operational substation and use the infrastructure there.
  • ACME Solar Holdings Limited is close to receiving stage one forest approval for the storage project and is discussing DPR approval with CEA.
    Show source
    We are very close to getting the stage one forest and we are in discussions with CEA for getting the Page 19 of 21 ACME Solar Holdings Limited May 20, 2025 DPR approved.
  • ACME Solar Holdings Limited has applied to the state for approval under the incentive scheme for the storage project.
    Show source
    So, and we already have applied to state for the incentive scheme approval as well.
  • The storage project has received approval. Replaced by a later filing.
    Show source
    So, that's the approval.
  • The project under discussion is under commissioning, and ACME Solar Holdings Limited expects to share its commission status maybe this week. Replaced by a later filing.
    Show source
    Maybe in this week, we will be able to share with you that commission.

Demand and pricing

  • The company expects tariffs for the remaining pure solar tenders to be between 2.7 and 2.8, given interest rates and integrated facilities.
    Show source
    So, you will see that it will be 2.7, 2.8.
  • Utilities are preferring FDRE and solar plus battery power because most utilities currently prefer evening and morning power. Replaced by a later filing.
    Show source
    So, they are preferring FDRE, solar plus battery, those type of powers.
  • The company is seeing good traction for merchant batteries. Replaced by a later filing.
    Show source
    So, we are seeing good traction even for the merchant battery.

Segments

  • More than 60%-70% of ACME Solar Holdings Limited's operational capacity is connected to the central grid, allowing the company to potentially play the merchant market on the battery side if it can execute faster.
    Show source
    So, out of our operational capacity, more than 60%-70% is now connected to the central grid.

Deals and partners

  • ACME Solar Holdings Limited has two partially signed PPAs: one for 190 megawatt and another for 200 megawatts of solar plus battery at a tariff of around 3.42; the company is hopeful they will be signed in a month or so.
    Show source
    One is this 190 megawatt and another is 200 megawatts of solar plus battery, which is at a tariff of around 3.42.
  • Battery suppliers are giving 20 years of warranty, with degradation leaving up to 70%.
    Show source
    Manoj Upadhyay: They are giving 20 years of warranty and with the degradation cycle, leaving up to 70%.
  • ACME Solar Holdings Limited's battery suppliers are all from China, which is the primary supplier for the lithium-ion phosphate batteries the company is procuring.
    Show source
    And they are all from China, of course, because as you know, China is the primary supplier for the lithium-ion phosphate batteries which we are procuring.

Risks, rules and outside factors

Outside factors

  • Power demand growth in FY '25 was around 4%, lower than expectations because of the higher base and higher than expected rainfall and favourable monsoon.
    Show source
    So, on the industry side, of course, the power demand growth in FY '25 was lower than expectations at around 4%.
  • Peak demand was 250 gigawatt in May last year and is expected to peak over 270 gigawatt this summer.
    Show source
    The peak demand was 250 gigawatt in May last year and is expected to peak over 270 gigawatt this summer.
  • India added around 30 gigawatt of renewable capacity during FY '25, bringing total RE capacity to over 220 gigawatts.
    Show source
    We added around 30 gigawatt during the year, bringing the total RE capacity to over 220 gigawatts.
  • Solar added 23.8 gigawatt of new installations during FY '25, taking total solar capacity to around more than 100 gigawatts.
    Show source
    Solar, of course, has been the leader with adding 23.8 gigawatt of new installations, taking the total solar capacity to around more than 100 gigawatts.
  • Wind reached around 50 gigawatt during FY '25.
    Show source
    And of course, the wind also reached a milestone of around 50 gigawatt.
  • New tenders for over 50 gigawatt were rolled out in FY '25, largely comprising hybrid and FDRE tenders incorporating battery storage.
    Show source
    So, new tenders were rolled out for over 50 gigawatt in FY '25, largely comprising of hybrid and FDRE tenders incorporating battery storage.
Show 4 more statements

Outside factors

  • Rajasthan gets around 5% to 10% higher radiation than the rest of the states, except some parts of Gujarat, which are at par with Rajasthan.
    Show source
    The second reason, which is more to do with the sunlight, is basically that the Rajasthan gets, you can say, around 5% to 10% higher radiation than the rest of the states, in terms of leaving apart some parts of Gujarat, which is at par with Rajasthan.

Rules and policy

  • ALCM will not allow ACME Solar Holdings Limited to import cells from China post-June 26, and this is already reflected in tariffs; there is not a large shift in tariffs, but this will help improve the attractiveness of current tariffs for the company.
    Show source
    Of course, as we move forward, we are seeing the impact of ALCM which is basically not allowing us to import cells from China post-June 26, to be correct.
  • Government policies require tariff adoption within a month of the bid and set a binding timeline for signing a PPA for new tenders.
    Show source
    So, now we have policies in place which require the tariff adoption to happen within a month of the bid.
  • None of the projects ACME Solar Holdings Limited has bid for are under the ambit of ALCM, but new bids come under the ambit of ALCM; ALCM will move tariffs up, giving the company a benchmarking benefit from having old PPAs.
    Show source
    So, in terms of the benchmarking, it gives us some benefit in terms of having the old PPAs because the ALCM will have an up move on the tariff.

Everything else said on the call

Other

  • The amount is around INR4,500 crores.
    Show source
    Arun Chopra: Yes, that's around INR4,500 crores.
  • The duty portion is close to around INR2100 crores. Replaced by a later filing.
    Show source
    Arun Chopra: So, as far as the duty number is, it's close to around INR2100 crores.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    Thank you for the opportunity. You highlighted that you have locked in the capex for the batteries. Can you share that number with us? What is the estimated or expected cost over there? And who would be the suppliers, I mean, based on the tiering?

    Answer, nikhil dhingra

    Nikhil Dhingra: Sure, Apoorva. Thanks a lot for joining the call. So, in terms of the capex, I will not be able to divulge specific numbers. But what I can tell you is that it is definitely much below the budget we had in terms of the initial bid budget. How do we plan for the project is, we take the current prevailing prices at the time of the bid. So, they are much below that. And of course, in terms of the tiering, they are all tier 1 suppliers.

    Answer, nikhil dhingra

    And they are all from China, of course, because as you know, China is the primary supplier for the lithium-ion phosphate batteries which we are procuring. So, the good thing is that there are enough and many suppliers which allow you to procure at scale and also procure within the timelines which you need. So, the good thing about batteries is that and good thing about our portfolio is that we have a large proportion of that in the central connected projects, right? So, out of our operational capacity, more than 60%-70% is now connected to the central grid. And that allows us to maybe, if we are able to execute faster, play the merchant market on the battery side. And that is another reason other than hedging the capex. We have also tried and preponed the battery side which of course can leverage the already operational substations we have with all the associated infrastructure.

    Answer, nikhil dhingra

    So, in terms of the capex, all I can tell you is that it's a very competitive price and that is why you are seeing the impact of that also in the tariffs. So, that's a good thing. Of course, there are counterbalances, the capex falls and various other things keep moving. So, like ALCM has also come in. So, there is a counterbalancing all the time in terms of tariffs. But all I can tell you is they are below the bid budget we had. And we will be able to share as we capitalize the asset because as you would appreciate, these are all competitive bids.

    Answer, nikhil dhingra

    So, it will not be wise for us to give the specific numbers.

  2. Question

    Apoorva Bahadur: Sure, sir. Correct me if my understanding is wrong, but I believe that the projects that we have already bid for are not under the ambit of ALCM, right?

    Answer, nikhil dhingra

    Nikhil Dhingra: In none of the projects which we have bid for are under the ambit of ALCM. But how it impacts us is that the new bids come under the ambit of ALCM. So, for the customers, new bids and old bids are the same, right? They care about the prices. It's a commodity, right? My power is not different from the earlier power, right? So, in terms of the benchmarking, it gives us some benefit in terms of having the old PPAs because the ALCM will have an up move on the tariff.

  3. Question

    Apoorva Bahadur: Okay. And last question on this battery side is that these suppliers, what sort of warranties do they give?

    Answer, manoj upadhyay

    Manoj Upadhyay: They are giving 20 years of warranty and with the degradation cycle, leaving up to 70%.

  4. Question

    Nihal Shah: Thank you for the opportunity and congratulations on the great set of numbers. So, my question was regarding capacity utilization factor. So, this year, our CUF is pretty high. And was it because of the new 1200 megawatt capacity that came in? What was the capacity utilization factor for that facility in the last quarter and for the old facilities in the last quarter, if we can bifurcate?

    Answer, nikhil dhingra

    Nikhil Dhingra: Sure. So, in terms of the capacity utilization factor for this new project which we have commissioned, we did more than 30% CUF, 32% to be exact in the last quarter. So, this is a very high CUF. Of course, you are right that operationalization of this 1200 megawatt project in Rajasthan and that too in the highest sunlight zone of Rajasthan, which is Fatehgarh, which has helped us get the CUF up to 25.6%2. And as you mentioned, Rajasthan as a state, if you look at our portfolio there, which is very large, that has done around 29.4% CUF on an annualized basis. So, as we move forward and we capture the full year impact of this project next year, the CUF is bound to go up. 2 Stated as 25.4% during the call, however, 25.6% is the correct reference Page 9 of 21 ACME Solar Holdings Limited May 20, 2025 Nihal Shah: Okay.

  5. Question

    And how much do we expect the CUF for the FDRE projects to be? And by when can we estimate our FDRE projects to commission in FY '26 and FY '27, if we can give a number?

    Answer, nikhil dhingra

    Nikhil Dhingra: Right. So, in terms of the C UF, it depends on the configuration and of course, it varies from bit to bit. But let's say there is a minimum CUF you need to give in each bid of around 40%, which is on an FDRE. And hybrid, it is typically around 30%. And in some FDREs, it is 50% minimum CUF. So, given our configuration, we are marginally above the minimum CUF in all these FDREs. So, you can say in a 40% bid, it will be around 43% to 45%.

    Answer, nikhil dhingra

    In a 50% bid, it will be around 50% to 55%. And of course, on a hybrid, it will be around more than 30%, maybe around 35%, 40%. So, that's the CUF, of course. So, that will give a higher revenue per megawatt of contracted capacity. Of course, it will have a higher capex per megawatt of contracted capacity as well. But of course, the return ratios are favorable, quite favorable.

  6. Question

    Nihal Shah: And so, the other question was, when can we estimate a pencil in some of the capacities of FDRE commissioning in FY '26 and '27?

    Answer, nikhil dhingra

    Nikhil Dhingra: Yes. So, as we mentioned that our base case is May -June, like when Mohit asked. So, May and June is the first FDRE schedule date. But what we'll try, wherever the substation is ready on a short-term open access basis, we'll try and commission it sooner by building the plant and the transmission line and every other thing. The issue with operating on STO is that you don't get a binding commitment to evacuate. So, that's a slightly lower realization of your capacity. But given that we are all geared up to execute faster, we will try and prepone this.

    Answer, nikhil dhingra

    But on the base case, it is May and June of '26.

  7. Question

    Nihal Shah: Okay. And when we talk about the cost of debt, so we've seen a reduction in INR7,700 crore debt that we have of 75 basis point. So, moving ahead, how much can we see a overall cost of debt reduction in the coming couple of years?

    Answer, nikhil dhingra

    Nikhil Dhingra: Right. So, we have only refinanced right now one of the project of ISTS, which is 300 megawatt out of the 1200 megawatt, which we recently commissioned. And that got us a rating of double AA-. So, as you know, interest rates are dependent on the credit rating. So, we are expecting that all of this 1200 megawatt should get a good rating in the similar band, which the earlier project has got. So, right now, if we borrow, we are typically getting 8.5% to 8.6% at that credit rating. Of course, it is expected to improve as the rates fall, which is again a macroeconomic thing.

    Answer, nikhil dhingra

    We are not really projecting it, but of course, it is likely to happen that in terms of the, if the rates fall, we are likely to get some benefit of the new refinancing. Of course, what we have refinanced already is locked in for a year. Page 10 of 21 ACME Solar Holdings Limited May 20, 2025 So, we'll not get a benefit for at least a year where we have already taken a disbursement. But where the sanctions are in place and we are dependent on our base rate, we may get benefit depending on when we take disbursement. So, it is expected to reduce and the reduction could be dependent on the base rates, which are expected to reduce. And of course, the improvement in credit rating allows us to get the best in class rate for an operational asset, which is around 8.5% today for a AA asset. Of course, we are taking long term financings.

    Answer, nikhil dhingra

    We are not taking a short term 5 year, 7 year financing. These are all long term financings we have taken for 20 years, which allows us to get free cash flow to equity, which we need to do capex and which allows us to improve the return ratios of the project also.

  8. Question

    Akash Mehta: Yes. Hi. Just, can you help with the capacity additions that we are kind of expecting in fiscal '26 and '27? I mean, you have given a number of 7 gigawatt by '27, '28. But if you can just help us with the year wise number. And second would be, I mean, any ballpark EBITDA that we could kind of be looking at in terms of forecast, yes.

    Answer, nikhil dhingra

    Nikhil Dhingra: Right. All right. So, on a FY '26 basis, we are very close to achieving our targets as per PPA timelines. 450 megawatt is what we are adding in this year. And that's the AC basis. On a DC basis, it could be, you can say 600 megawatt peak around that number. In terms of the FY '27, bulk of our capacity is coming up in FY '27, which is as per the signed PPAs, which we just mentioned around 2.2 gigawatts, right?

    Answer, nikhil dhingra

    So, 2.2 gigawatt of capacity is coming up in FY '27 because all of their PPA has been signed. So, Ankit, correct me if I'm wrong. 2.2 gigawatt is what should come up in.

    Answer, nikhil dhingra

    Nikhil Dhingra: 1.89 gigawatt in FY '27. And then, of course, we are building the rest of the plants also. But I'll be able to give you the timeline once the PPA gets signed. But that is something which we are expecting in FY, beyond FY '27, where the PPAs have not been signed, but we have begun construction. So, our execution will not get delayed. But of course, we will not do capex until the PPA gets signed. So, that is the capacity which will shift beyond FY '27.

    Answer, nikhil dhingra

    But we have already blocked connectivity’s, which allows us to commission before FY '27. But we will get, let's say, a grace period to commission post FY '27 also, because you get 2 years to commission post PPA signing. So, the rest of the capacity you can put beyond FY '27, which, Ankit, you can quantify what's that number. Page 11 of 21 ACME Solar Holdings Limited May 20, 2025 Ankit Verma: It's roughly around 2 gigawatts.

  9. Question

    Akash Mehta: Okay. I think that's helpful. And I mean, in terms of incremental bidding, so since there are a lot of things in pipeline, you'll be looking for more projects or probably you'll be looking to enter, maybe you'll take a break, maybe for 6 months or a year, and then looking at more projects for your 10 gigawatt target for fiscal '30.

    Answer, nikhil dhingra

    Nikhil Dhingra: Yes, yes. So, see, you're right. In terms of the bidding space and time, we've already taken that. We have not won in last, as you would have seen in the last 6 months, we have not won much capacity. Of course, the bids have been also slow. But in this industry, what you have to also realize is that it's a question of optimizing tariffs and optimizing the construction timelines. So, what we are trying to do, rather than being aggressive on the bids, is being aggressive on the execution ahead of time, like we have already built a merchant plant in Sikar.

    Answer, nikhil dhingra

    So, that plant is a very big strategic advantage for us because we can plug into any of these PPAs which we get or which we have not got still and commission it immediately. And considering the merchant market today, we have a very healthy tariff going on for the next couple of years, given the peak deficit. So, what we are trying to get is some of the connectivities which we have. We will try and build those connectivities. And we are able to get financing also for the merchant plants. So, we will keep on building these plants once we get financing. We will not build a plant where we don't get financing on the debt side because we want to cover our risks.

    Answer, nikhil dhingra

    And of course, we will put them into a PPA when we get a good bid. And of course, we will always try to be financially prudent in terms of scheduling our capex as per the available resources, because we don't intend to raise any further equity for funding the capex we have. So, we will always try and bid conservatively. In terms of the new project profile, they are all coming with storage. And so, the capex per bid has reduced because they have less of wind capacity and more of solar and battery. So, capex has reduced. But still, we will try and basically stagger our PPAs and stagger our commissioning timeline such that we reach 10 gigawatts, but we reach in a way which is yearly-wise more balanced and concentrated in a particular year.

  10. Question

    Dhruv Muchhal: So, if you can share what that number is of the duty portion.

    Answer, nikhil dhingra

    Nikhil Dhingra: So, it's around INR4,500 crores. Correct me if I'm wrong, Arun, right?

    Answer, arun chopra

    Arun Chopra: So, as far as the duty number is, it's close to around INR2100 crores.

    Answer, arun chopra

    Arun Chopra: Yes, that's around INR4,500 crores.

Show 9 more questions
  1. Question

    Dhruv Muchhal: So, the duty portion within the gross is about INR2100 crores.

    Answer, nikhil dhingra

    Nikhil Dhingra: That is for the six projects. That is not for the 1200 megawatt. So, for the 1200 megawatt, it will be around INR1,400 crores.

  2. Question

    Dhruv Muchhal: INR1,400, yes. One second, if I just said just INR1,400. So, yes, perfect. Makes sense. So, the second question is, as you mentioned, the ALCM probably leads to an increase in tariffs. So, the industry understanding is the tariffs for pure vanilla solar can go to about INR3, INR3.1, approximate. I don't know if people get more aggressive. But when I look at your pipeline projects, for example, you have an Omega project, if I'm not wrong, which is Omega Urja solar of 300 megawatt, which if I'm not wrong, the tariff is about INR2.5. So, I'm just curious why this project does not get signed, because the new tariffs will come at, say, vanilla solar will come at INR3, and you have

    Answer, nikhil dhingra

    Nikhil Dhingra: Right, right, right. So, I think the one thing is that on the ISTS waiver front, it's the commissioning date, and it's not the PPA signing date. So, there is no advantage, per se. But of course, you're very right that INR2.52 is a very attractive tariff, and we are expecting that PPA Page 13 of 21 ACME Solar Holdings Limited May 20, 2025 to get signed very soon. So, it's something which you're right that the tariffs will be higher going forward. And of course, what the other thing is happening is, there are no pure solar bids coming. They are now going to come up with some component of battery, right.

    Answer, nikhil dhingra

    So, these are some of the few remaining pure solar tenders. And given the overall profile of having some bit of peak power, so these are, you can say, the residual solar, which is going to get picked up very soon. So, you're right that it is an attractive tariff. But like you rightly said also, the aggression also is there. Sometimes the tariff should be 3, but may not be 3, right. So, you will see that the tariff will be somewhere between, not in the very, this thing, because the interest rates, and of course, the people have integrated facilities. So, you will see that it will be 2.7, 2.8.

    Answer, manoj upadhyay

    So, there are actually few PPAs or few tenders, which are still open in the pure solar category, and they will get signed. Price-wise, it is very attractive, it should get signed. But right now, most of the utilities are preferring evening and morning power. So, they are preferring FDRE, solar plus battery, those type of powers.

  3. Question

    Sure. And just the next question was on the point of, you know, pre-poning some of your FDRE projects, I think the battery portion. So, I am just trying to understand how does it help. Can you start supplying to the discom if you pre-pone it or you are looking at optimizing it on the merchant basis because probably you commissioned the battery portion of the project early and optimize by selling it on the grid because you have that leeway available for a few months. Is that what you are… Nikhil Dhingra: Right.

    Answer, nikhil dhingra

    Right. So, see, there are facilities available in the PPA where you could procure the battery power from a third party, which is basically you can have it on a merchant basis till the time you plug it into a PPA. So, what you can do till the time you plug into a PPA, you can install the batteries on an already operational substation and use the infrastructure there. And when the PPA, the rest of the component is ready, you can start supplying to that PPA. Dhruv Muchhal: Okay. So, until the PPA official, I mean, is commissioned, till that time you will be selling the power on merchant basis?

  4. Question

    Dhruv Muchhal: Okay. And I mean, speaking to some, it seems that I am not very clear about funding for battery projects because -- so, is the funding for battery projects now available or still there is some hurdle in terms of warranties and insurance and all those claims from the lenders?

    Answer, nikhil dhingra

    There is a PLI scheme. There is a lot of state governments are also buying large amount of batteries. So, the understanding about the battery has really improved in the last year or so. And everybody realizes that this is a good capex and it should be supported. So, we are seeing good traction even for the merchant battery.

  5. Question

    Anit Suri: Yes. Hello. Hi, sir. So, just a quick question on the CUF. So, just wanted to check, you mentioned that the Rajasthan capacity has a CUF of 29.4% as opposed to the overall CUF of 25.6%. Is there any specific reason why this has a 4% higher CUF than the rest of the capacity? Maybe like a different kind of technology or something?

    Answer, nikhil dhingra

    So, all of our old projects have some kind of limitation around that. Post-2017, which we have signed from the central REIAs, this cap was removed. So, post-2017 projects don't have this cap. The second reason, which is more to do with the sunlight, is basically that the Rajasthan gets, you can say, around 5% to 10% higher radiation than the rest of the states, in terms of leaving apart some parts of Gujarat, which is at par with Rajasthan. But it gets a higher radiation than other states. So, because of the higher proportion of the power being located in Rajasthan, we also get advantage of that. And everybody gets advantage of that, whoever is located in that region.

    Answer, nikhil dhingra

    The third reason, which is, again, the technical configuration of plants, which have been consistent. It's not a new thing for us. We have been doing higher CUF, because in terms of the sharing the AC infrastructure with the larger DC infrastructure by putting more modules of around 1.5 times overloading on each inverter. So, that is, again, a technical point, which helps us to generate this kind of CUF, because given the cost benefit, it makes sense to install more modules over the same AC infrastructure. So, these are the three reasons. The Rajasthan has a higher sort of CUF than, let's say, some of the older PPAs So, primary reason is regulatory, and the rest two reasons are, you can say, contributing also. Management: And just to add here, one more point.

  6. Question

    Anit Suri: Got it. Understood. That makes sense. The second question I have is in terms of funding. So, regarding the funding, you mentioned that INR16,000 crores of funding has been secured for the Page 16 of 21 ACME Solar Holdings Limited May 20, 2025 under-construction capacity. So, is that going to be fully debt-funded? I just wanted to understand if the INR16,500 crores is the entire number, or are we funding something from internal accruals as well?

    Answer, nikhil dhingra

    And let's say 75:25 or 80:20 debt-to-equity. So, let's say one-fourth of this number is the equity we need. So, we do have that already. So, you can say the INR16,5003 crores of debt will be supplemented by around INR4,000 crores of equity, and that will help us do INR20,000 crores of capex.

  7. Question

    Anit Suri: Understood. And just a last one, if I can ask, maybe this has already been answered, but regarding the BESS commissioning, is there any specific timeline that you provide?

    Answer, nikhil dhingra

    Nikhil Dhingra: Right. Like we said, we are doing one pilot project, which will be executed in our operational sites in 200 megawatts. So, that we are targeting for Q2, the later part of Q2. That's a pilot project. But large-scale project, we are targeting to do in Q3. So, we've already done the tie -ups, like we mentioned. So, depending on all the components and all the approvals, that's something we are trying to do, because we are also very geared up to utilize the gap between the peak power rates and the base power.

  8. Question

    Anuj Upadhyay: Fair enough, sir. Secondly, sir, on your FY '30 target, so currently we are at, say, 2.7 operational. We'll be adding, say, another 3.5 or 4.5 gigawatt capacity by FY '27-'28. And from there till FY '30, we are targeting around 10 gigawatts, just to get a sense, aren't we too conservative in terms of capacity addition target or there's some huge potential to revise this target going ahead? And lastly, any thoughts of getting into pump hydro or any othe r storage design?

    Answer, nikhil dhingra

    Nikhil Dhingra: So, Anuj, there are two things there in terms of this target. So, when we talk about target, we talk about contracted capacity and we don't talk about installed capacity. Some of the companies talk about installed capacity, which will be, let's say, for us also more than 20 gigawatts when we install this around 10 gigawatts or because the solar and the battery and various other Page 18 of 21 ACME Solar Holdings Limited May 20, 2025 equipment which go is multiples of the contracted capacity. For a 250 megawatt plant, let's say we will have more than 500, 600 megawatts of installed capacity. So, we are not focused on boosting these gigawatt targets because ultimately it's about profitability. So, we don't really document it on a installed capacity basis, but our number will be quite high on installed capacity numbers and we can share with you that number. But in terms of contracted capacity, which determines your revenue and CUF, this is 7 gigawatts is what we are trying to reach.

    Answer, nikhil dhingra

    And as we move forward, this 10 gigawatt again is a combination of FDRE and hybrid. So, this will be leading to a huge number on installed capacity, which will be 20 gigawatt plus. So, that is one. And secondly, in terms of the execution capacity of a single corporate. So, right now, Andwe are an integrated player with EPC built in and these are all large infrastructure projects. So, in terms of the increasing our ability to execute more, right, the land is one of the primary constraints because you get to -- you need a large parcel of contiguous land, which government land can help you get there. So, we are trying, like we mentioned earlier, we are trying to secure a large portion of lands, which will help us improve this on a per year execution.

    Answer, nikhil dhingra

    So, we are oriented in the direction which the market is today. And we will keep on developing the asset. But we will not do capex until we get a good tariff, which is in sync with the construction risk of a PSP. Anuj Upadhyay: That's helpful. And what quantum this PSP would be in UP, which you mentioned?

    Answer, nikhil dhingra

    Nikhil Dhingra: It's a 600 into 6 megawatt hour of storage, 6 hours of storage. So, that's the approval. We are very close to getting the stage one forest and we are in discussions with CEA for getting the Page 19 of 21 ACME Solar Holdings Limited May 20, 2025 DPR approved. So, and we already have applied to state for the incentive scheme approval as well.

  9. Question

    Anuj Upadhyay: Fine, sir. That's quite helpful. Thanks. And wish you good luck.

    Answer, manoj upadhyay

    Manoj Upadhyay: Good morning. I would like to start with, while Nikhil has touched upon the performance of the year, but I would like to also mention some of the area we could have done better. I think PPA signing, we were expecting to sign 400 to 500 megawatt last quarter, but unfortunately it shifted to this quarter. So, this forecasting of signing the PPA is one learning I think we have to build inbuilt in our system. Although we have a very limited control, how the REIA deals with the state government, but this area I think I would like my team to work on. So, we are able to give you this thing. Second area is I think we wanted to do our Sikar 300 megawatt solar plant.

    Answer, manoj upadhyay

    Maybe in this week, we will be able to share with you that commission. I would like to highlight that we continue to focus on the technology innovation and execution to build a future-ready and sustainable portfolio. We want to cater to India's requirement of growing energy demand. And I see that this will more happen right in the FDRE or a base power or a peaking power, instead of the solar time or wind time power. You will see more and more such adoption, and we are ready to do that. And as a company, we have been testing this solution for quite a long. Page 20 of 21 ACME Solar Holdings Limited May 20, 2025 We have made remarkable progress this year.

Questions about this call

When was the Acme Solar Holdings Q4 FY25 earnings call transcript filed?
Acme Solar Holdings filed the transcript with the exchange on 26 May 2025. This page is built from that transcript.
What does this page list?
65 statements from the transcript across 10 topics, 46 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 19 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.