Acme Solar Holdings Q3 FY25 earnings call: Acme Solar Holdings Limited won 1,900 MW of capacity in this financial year

By . Assembled by software from the company's transcript. Not reviewed by a person.

Transcript filed .

The company won 1,900 MW of capacity in this financial year. Operational capacity of 2,540 MW will give it a run rate annual project to bid of around INR 1,750 to INR 1,800 crores. The company increased capacity by 90% to 2,540 MW through commissioning 1,200 MW of solar capacity tied up with SECI; its operational portfolio is 2,540 MW and its GW peak is 3.6 GW peak. ACME Solar Holdings Limited's operational capacity increased to 2,540 MW from 1,340 MW as of Q1FY25, an approximately 90% expansion, on account of 1,200 MW SECI ISTS projects energised in October 2024. Pre-tax ROCE is 14.5%. The company sees all four REIAs stepping up bidding this year to try to achieve the government's 50 GW targets.

The numbers management gave

Results

  • Pre-tax ROCE is 14.5%.
    Show source
    And in terms of the ROCE, which is basically pre-tax ROCE, we do 14.5%.
  • Total revenue for Q3 FY'25 was INR 401 crores, up 45% on an adjusted basis and 10% on a reported basis, mainly on account of phased commissioning of the recent SECI ISTS 1200 MW plant.
    Show source
    So, our total revenue for the quarter stands at INR 401 crores which is up 45% on adjusted basis and 10% on reported basis.
  • EBITDA for Q3 FY'25 was INR 359 crores, up 59% on a like-to-like comparison basis and 15% on a reported basis.
    Show source
    3 Stated as ROC during the call, however, Gross Block (less EPC margin realized within Acme group) is correct ACME Solar Holdings Limited January 29, 2025 EBITDA for the quarter stands at INR 359 crores which is substantially up 59% on a like-to-like comparison basis and 15% on reported basis.
  • Reported EBITDA margin was 90% in Q3 FY'25 on account of higher operating leverage because it has a higher base of operational assets.
    Show source
    As far as margin s are concerned, they are like 90% on the reported basis on account of the higher operating leverage , because now we have higher base of operational assets.
  • PAT for Q3 FY'25 was INR 112 crores, up 152% on a reported basis and 317% on a like-to-like asset basis.
    Show source
    And our PAT for the quarter stands at INR 112 crores, which is up 152% on reported basis and 317% on a like-to-like asset basis.
  • Cash PAT for Q3 FY'25 was INR 189 crores, up 52% on a reported basis and 149% on a like-to-like asset basis.
    Show source
    Our cash PAT for the quarter is INR 189 crores which is up 52% on reported basis and up 149% to be precise on like-to-like asset basis.
Show 40 more statements

Results

  • PAT margin for Q3 FY'25 was 28%, compared with 12% in the last quarter on a YoY basis.
    Show source
    And the last thing here is the PAT margin, which is for the quarter is 28% as compared to 12% in the last quarter o n YoY basis.
  • Revenue for the nine months was INR 1,036 crores, with EBITDA of INR 917 crores and an EBITDA margin of roughly 89%.
    Show source
    So, for the nine months , –total revenue is INR 1,036 crores with an EBITDA of INR 917 crores, which reflects EBITDA margin of roughly 89%.
  • Standalone financials for the nine months, reflecting profitability from its in-house EPC business for its own subsidiaries, show total revenue of INR 1,203 crores, EBITDA of INR 407 crores, and PAT of INR 199 crores.
    Show source
    And on the standalone financial basis, which reflects our profitability from the in-house EPC business that we do for our own subsidiaries, our total revenue for the nine months is INR 1,203 crores with EBITDA of INR 407 crores and PAT of INR 199 crores respectively.
  • The company paid 6 crores of taxes on a standalone basis in this quarter; there is no tax on power sale on a consolidated basis.
    Show source
    So, in this quarter on the standalone basis, we paid 6 crores of taxes in this quarter.
  • Interest on fixed deposits was around 30-odd crores in this quarter.
    Show source
    Arun Chopra: So, on the other income side, so interest on FD are -- is close to around 30-odd crores.
  • Amortization of deferred revenue was around INR 15 crores in this quarter.
    Show source
    Arun Chopra: Another 28 majorly include amortization of the deferred revenue of around INR 15 crores.
  • Standalone employee benefits increased from INR 24 to INR 36 crores, while consolidated employee benefits were reasonably constant in Q3 FY'25.
    Show source
    So, on the standalone basis, our employee benefits have moved up from INR 24 to INR 36 crores and on a, on a consol basis, they are reasonably constant.
  • The company sold power in the range of INR 2.7 to INR 3 in the past quarter or so and has more than INR 3 as the average tariff for its 300 MW merchant plant.
    Show source
    So, that's the tariff you can assume on an average basis more than INR 3 we have for the merchant plan of 300 MW.
  • Costs increased from the last quarter because employees transferred from ACME Cleantech to ACME Solar Holdings; it does not expect head-office costs to rise going forward, while hiring for projects will be included in each project's cost.
    Show source
    So, it has increased because of that.
  • CUF was 23.7% as compared to the last year and is going to increase because the proportion of high CUF projects has increased in the portfolio. Replaced by a later filing.
  • The company sold around 250 crore units in these nine months, a jump of 34.5% in units. Replaced by a later filing.
  • Plants are running at 99.4% availability and grid availability is 99.6%. Replaced by a later filing.
  • The project contributed INR 80 crores of revenue in Q3 FY'25, and its EBITDA was 90%. Replaced by a later filing.

Money and capital

  • Net debt was INR 6,882 crores in this quarter, compared with INR 8,755 crores in the previous quarter.
    Show source
    So, net debt is now at INR 6,882 crores in this quarter as compared to INR 8,755 crores in the previous quarter.
  • The company has sanctioned INR 16,500 crores in Greenfield financings; it has sanctioned debt for 1,700 MW of its 4,400 MW under-construction projects, amounting to around INR 16,500 crores; 1,700 MW is around 40% of under-construction projects and around 80%-90% of its signed PPAs of around 2,300 MW.
    Show source
    In terms of the Greenfield financings, we have sanctioned INR 16,500 crores.
  • The company refinanced 50-55% of its debt, around INR 5,500 crores, at an average rate of 8.8% per annum; Acme Solar Holdings Limited has refinanced more than 50%-55% of its current debt at average rates of 8.8%, with refinancing expected to reduce rates by roughly 70 bps for the projects refinanced.
    Show source
    And in terms of the refinancing, we have refinanced essentially 50-55% of our debt, which is around INR 5,500 crores, so at an average rate of 8.8% per annum.
  • Net operational debt-to-EBITDA on an annual EBITDA basis for the current financial year will be around 5X, below its guided range of 5.5X.
    Show source
    And if you look at our some of the key metrics in terms of net debt-to-EBITDA, so if you look at the net operational debt on an annual EBITDA basis for the current financial year, it will be around 5X, which is below our guided range of 5.5X.
  • Net debt-to-equity after raising primary capital from the IPO stood at 1.6X.
    Show source
    And net debt-to-equity after raising the primary capital from the IPO currently stood at 1.6X.
  • The company has factored around INR 12 crores for RSUs to be issued through senior management in its standalone financials in Q3 FY'25.
    Show source
    Manoj K Upadhyay: We've also taken consideration of RSU, because we have also factored the RSU will be issued through the senior management, that is also actually a method in the standalone, that's around INR 12 crores, right.
  • The company plans to finish the projects by 2028, with some projects possibly commissioned in '26 and some in '27, and does not see an equity gap in the capacity it has won because phase-wise commissioning increases accruals through securitization, cash flows and EPC margins.
    Show source
    So, because of this phase wise commissioning, we don't see that we will have an equity gap in terms of ACME Solar Holdings Limited January 29, 2025 this capacity which we have won.
  • The company raised INR 650 crores through securitization in these nine months by refinancing INR 5,500 crores, yielding INR 650 crores of top-up; it can obtain around 13% more debt against its debt, and this is not a sale of assets.
    Show source
    Like we have mentioned in our presentation, we have raised INR 650 crores of securitization in these nine months, which you can see that we have refinanced on Slide #6, INR 5,500 crores of refinancing which have yielded INR 650 crores of top up.
  • The company had done roughly INR 3,500 crores of CAPEX in nine months for this particular year.
    Show source
    Management: So, in nine months, we have done roughly INR 3,500 crores of CAPEX for this particular year.
  • The company expects to do around INR 800 crores of CAPEX in the next six months, in the next two quarters.
    Show source
    I think less than that, it should be less than that, around INR 800 crores of CAPEX we will be doing in the next six months in next two quarters.
  • Actual CAPEX is INR 4,600 crores.
    Show source
    If you, if you look at the, I think the actual CAPEX, so INR 4,600 crores.
  • The company has obtained rates of 8.6 and 8.5 for some refinancing projects, and the refinanced projects have a rating of AA-.
    Show source
    See, sometimes what happens is, it is a tradeoff between taking securitization proceeds and the rate because you have to take a call , definitely lower rates are possible just to answer your question, definitely lower rates are possible , because the rating of these projects, already we have managed to get AA- for our refinancing.
  • Around 70% of Acme Solar Holdings Limited's operational PPAs are with AAA counterparties.
    Show source
    So, as we said on the operational side also, around 70% is AAA.
  • The company said that if some products with a Single A rating reach AA, their rates will fall by 25 to 30 basis points.
    Show source
    But if we manage to go to AA, the rate will fall by let's say 25 to 30 basis points.
  • The company said it raised INR 2,400 crores of IPO money, its most significant source for the INR 7,500 crores equity requirement.
    Show source
    So, we have raised INR 2,400 crores of IPO money, right.
  • The company said it had raised around INR 650-odd crores of securitization proceeds in these nine months and expected the SECI project to add at least INR 1,000-odd crores in securitization proceeds.
    Show source
    And of course, the SECI project we just updated you, will add at least INR 1,000-odd crores in terms of securitization proceeds.
  • The company said securitization will add around INR 2,500-odd crores on top of the INR 2,400 crores it has from the IPO.
    Show source
    So, you can say securitization will add around INR 2,500-odd crores on top of the INR 2,400 crores we have from the IPO.
  • The company said construction margins are a third source of equity and guided to 5% to 7% EPC margins.
    Show source
    Like we guided you on the 5% to 7% EPC margins.
  • The company said it can expect EPC accruals of around INR 2,000 to INR 2,500 crores from what it constructs from INR 45,000 crores.
    Show source
    On whatever we construct from this INR 45,000 crores, so you can expect EPC accruals of around INR 2,000 to INR 2,500 crores.
  • Refinancing reduces its cost of debt and releases cash, which is a source of accruals for future funding.
    Show source
    One is the reduction in cost of debt and second is the cash release, which is one of the sources of accruals for us in terms of the future funding.
  • The company is borrowing more at variable rates so its rates can come down as MCLR comes down.
    Show source
    Because what we are trying to do is borrow more on the variable rates and which will help us come down as the MCLR comes down.
  • The company said rates can come down depending on each specific product as ratings are upgraded.
    Show source
    Because the rating upgrades, the rates can come down depending on each specific product.
  • The company said free cash flow from running projects will provide a buffer for more cash flows than required.
    Show source
    So, that will also give us buffer to have more cash flows than required.
  • The company used all of the IPO proceeds to reduce debt, reducing debt by around INR 2,070 crores. Replaced by a later filing.
  • The company has sanctioned debt for 1,700 MW of its 4,400 MW under-construction projects, amounting to around INR 16,500 crores; 1,700 MW is around 40% of under-construction projects and around 80%-90% of its signed PPAs of around 2,300 MW. Replaced by a later filing.
  • The company does not think it will need to raise equity for the capacity it has won, as commissionings through 2028 and cash flows, securitization and EPC margins from those three years will help fund the projects. Replaced by a later filing.
  • The company has refinanced more than 50%-55% of its current debt at average rates of 8.8%, with refinancing expected to reduce rates by roughly 70 bps for the projects refinanced. Replaced by a later filing.

What it expects ahead

What management expects

  • Operational capacity of 2,540 MW will give it a run rate annual project to bid of around INR 1,750 to INR 1,800 crores.
    Show source
    1 Stated as portfolio split during the call, however, operational portfolio is the correct reference 2 Includes projects where tariff has been adopted or order reserved ACME Solar Holdings Limited January 29, 2025 In terms of the next slide, capacity road map, so 2,540 MW, which is operational for us will give us a run rate annual project to bid of around INR 1,750 to INR 1,800 crores.
  • The company will be operating 6,970 MW of capacity by FY'27-28 in the base case, while it will make all efforts to prepone this.
    Show source
    We will make all efforts to prepone this, but in the base case we have 6,970 MW of capacity which we will be operating by FY'27-28.
  • The company intends to commission 350 MW in Q3 FY'25, though it may spill over to April in the worst case; it intends to commission 100 MW of wind between the June to September quarter.
    Show source
    So, that is the intent that 350 MW gets fully commissioned.
  • Of Acme Solar Holdings Limited's 350 MW project expected to go online, 50 MW is a wind project at a tariff of INR 2.907, and wind projects typically have a CUF higher than 30%.
    Show source
    So, of the 350 MW project, 50 MW is at a tariff of INR 2.907.
  • The company has a PPA at 3.05 for its 300 MW merchant plant; if the PPA is signed before June, revenue on the 300 MW is 3.05, otherwise it is closer to 3, and the plant will be operating at 30% CUF.
    Show source
    So, if the PPA gets signed before June, so the 3.05 is the revenue on the 300 MW and otherwise closer to 3 only.
  • The project can generate annual EBITDA of around INR 720-odd crores at 30% CUF and, at its best, around INR 180 crores, but is seasonal.
    Show source
    It is of course this project can do an annual EBITDA of around INR 720-odd crores if you take 30% CUF.
Show 11 more statements

What management expects

  • The company plans to operate its merchant project for three, four or five months and then transfer it under a PPA at an INR 3.058 tariff for 25-years.
    Show source
    And we have already found a PPA where we will fix -- we will transfer this project, right, at INR 3.058 tariff for 25-years.
  • The company said it had created a pipeline beyond '26 and would focus future pipeline creation towards '28 to '30 timelines to achieve its 10 GW target.
    Show source
    And our focus will remain that any future pipeline or whatever we create, we create towards '28 to '30 timelines, so we achieve a 10 GW, our target.
  • The company expects a much better CUF number from the next quarter.
    Show source
    So, from the next quarter you will see much better number on the CUF.
  • The company is positive that the NTPC PPA will be signed shortly.
    Show source
    And in terms of the other ones, so we are quite positive that the NTPC once again will be signed shortly.
  • The company is hopeful that the remaining PPAs will be signed in a couple of months at most; the top two will be signed very quickly and the others are at an advanced stage.
    Show source
    But we understand is the top two ones will be signed very quickly, the rest of them are also very advanced, but of course and we are hopeful that they will be done in max couple of months.
  • The company is hopeful that the power offtake agreements for the capacity highlighted under the LOA will be signed soon, as tariffs have been adopted recently and are in the range of what it has done in the last two years.
    Show source
    So, we are quite hopeful that they will be signed soon.
  • The company expects the rating upgrade following its overall equity raise and repayment of corporate-level debt on the consolidated level to help it obtain lower rates in upcoming quarters.
    Show source
    So, we will basically get the upside of that in the upcoming quarters .
  • The company expects credit-rating improvement after the IPO and said its team is working to improve its credit rating.
    Show source
    So, we expect a credit rating improvement because after IPO we expect that to happen .

Orders

  • The company won 1,900 MW of capacity in this financial year.
    Show source
    In terms of the new orders and growth side, we have won 1,900 MW of capacity in this financial year.
  • Total contracted portfolio is 6.97 GW.
    Show source
    So, our total contracted portfolio is 6.97 GW.
  • Of the 1,900 MW won by Acme Solar Holdings Limited, 1,000 MW is FDRE peak power contracts, 600 MW is solar, and 300 MW is hybrid.
    Show source
    And in this 1,900 we have FDRE, which is the peak power contracts of 1 ,000 MW, solar of 600 MW and hybrid of 300 MW.

What it is building and selling

Projects and capacity

  • The company increased capacity by 90% to 2,540 MW through commissioning 1,200 MW of solar capacity tied up with SECI; its operational portfolio is 2,540 MW and its GW peak is 3.6 GW peak. ACME Solar Holdings Limited's operational capacity increased to 2,540 MW from 1,340 MW as of Q1FY25, an approximately 90% expansion, on account of 1,200 MW SECI ISTS projects energised in October 2024.
    Show source
    So, we have increased by 90% and this is due to the commissioning of our 300x4, 1,200 MW of solar capacity which is tied up with SECI.
  • The company has signed 2,340 MW of PPAs out of 4,430 MW of under-construction capacity; around 2,090 MW of the PPA capacity remains to be signed.
    Show source
    I think you're more interested in what will happen to the rest of the PP A which is around 2 ,090 MW, right?
  • The company has signed PPAs and completed tariff adoption or has orders reserved for more than 53% of its under-construction capacity.
    Show source
    So, in both these regards, we are of more than 53% of our under-construction capacity.
  • 450 MW of Acme Solar Holdings Limited's capacity is in advanced stages of construction.
    Show source
    450 MW of our capacity is in advanced stages of construction.
  • The company has grid connectivity in place for 100% of its under-construction capacity and all the capacity highlighted under the LOA, and is moving forward on land and transmission lines to get a head start when the PPAs are signed; around 2,000 MW is available for future bids.
    Show source
    In terms of the grid connectivity, we have the grid connectivity for all of them.
  • The company has LOA for around 4.45 GW of capacity.
    Show source
    We have LOA for all of this capacity, right, which is around 4.45 GW.
Show 19 more statements

Projects and capacity

  • Of the capacity discussed, 2,340 MW has seen the PPA, while the whole of 2,090 MW is yet to see the PPA.
    Show source
    So, the 2,340 has seen the PPA MW, 2090, the whole of it has to see the PPA.
  • The company has close to around 5,000-odd acres of land for under-construction projects and land at around 104 wind locations for these projects.
    Show source
    So, we will give you update on the solar side and wind side both , so we are close to around 5,000-odd acres land for the under- construction projects and for the wind location around 104 locations we have the land for these projects.
  • The company aims to have land in place for projects with signed PPAs within six months of PPA signing, and in the worst case within around 9 to 12 months.
    Show source
    And in terms of the timelines, this is -- we are acquiring land even for projects which are far ahead sometimes and, and of course our aim is, like we said, in terms of prioritization, our aim is that for the PPA signed projects, the land should be in place ideally within six months of the PPA signing, completely done and in, in worst case, around 9 to 12 months.
  • The company said it starts buying land where it takes connectivity, and this land acquisition is less than 1% of CAPEX.
    Show source
    So, we start buying land at the place where we take connectivity, but that is less than 1% of the CAPEX.
  • The company said land CAPEX is reusable and is not sunk if there is an issue with the option.
    Show source
    But of course, and this CAPEX is reusable, this is not something which is sunk if there is any issue on that option and all things.
  • The company said it does not undertake non-recoverable CAPEX before the tariff is adopted.
    Show source
    So, we don't do CAPEX, which is non-recoverable before the tariff is adopted.
  • The company said it will set up one small FDRE project in this quarter or the next three to four months to test new technology.
    Show source
    So, we want to also do that, put the new technology in test and I think in this quarter or next three, four months, we will set up one small FDRE project because I have seen in many interaction that people had some concern on FDRE, although, yes, FDRE is not this thing because we have been forecasting our power under deviation settlement mechanism for last four, five years.
  • The company has signed PPAs for 2,340 MW; around 2,090 MW of the PPA capacity remains to be signed. Replaced by a later filing.
  • The company has grid connectivity for all the capacity highlighted under the LOA and is moving forward on land and transmission lines to get a head start when the PPAs are signed. Replaced by a later filing.

Demand and pricing

  • The company sees all four REIAs stepping up bidding this year to try to achieve the government's 50 GW targets.
    Show source
    But of course, in terms of the bidding this year we see all the four REIAs stepping up and trying to achieve the 50 GW targets which the government has given .

Segments

  • Central offtakers constitute 67% of Acme Solar Holdings Limited's operational portfolio and states constitute 33% of the portfolio.
    Show source
    ACME Solar Holdings Limited January 29, 2025 In terms of the operational1 portfolio split, now, the central offtakers constitute 67% of our portfolio and states only constitute 33% of the portfolio, which is of course improving the credit rating of the overall portfolio and overall utility business we have.
  • The company has no sales to the US because it is a utility; all its sales are under 25-year PPAs to utilities in India, and all its revenues are in rupees.
    Show source
    And in terms of the sale, all of our sale is in 25-year PPA to the utilities in India.
  • The company has only 300 MW of merchant capacity and intends to operate it as merchant capacity only until it finds a PPA; it has found a PPA through the SECI tender at INR 3.05.
    Show source
    And we have found that with the SECI tender of INR 3.05 which we have won.
  • The company said battery-backed forecasting will improve its existing forecasting under the deviation settlement mechanism.
    Show source
    So, technically it is the same deviation settlement mechanism and forecasting with the battery inside which will improve it further.

Deals and partners

  • The PPAs for the 380 MW and 350 MW FDRE projects with SECI are expected to be signed shortly; half of the PPAs have been signed, and an order has been reserved for a tariff.
    Show source
    So, in terms of the two projects, 380 MW of FDRE with SECI and 350 MW FDRE with SECI again, half of the PP As have been signed.
  • The company won a bid from SECI at INR 3.056 and plans to move the 300 MW merchant project to one of its PPAs; the SECI PPA requires power supply before June '25.
    Show source
    Just on this merchant plant, I would like to say that we have won a bid at -- from SECI at INR 3.056, which we of course like we had earlier also mentioned we plan to move this merchant to any of our PPAs.
  • SECI has signed up with Chhattisgarh for 190 MW and is talking to that state for the rest of the capacity.
    Show source
    So, what we understand is that they are in discussion with a few state governments, principally some of the states which they have already signed up with, like SECI has signed up with Chhattisgarh for 190 MW.
  • SECI is talking to Uttar Pradesh and Madhya Pradesh about PPA signing for the remaining capacity.
    Show source
    So, that is the one party which they are talking to for the rest of the capacity… and of course they're talking to Uttar Pradesh, Madhya Pradesh for this.
  • The company signed a PPA for 680 MW for its NHPC bid yesterday, after UP had done 1,200 MW for that bid. Replaced by a later filing.

Risks, rules and outside factors

Outside factors

  • Cell accounts for around 25% of the overall module price, and around 12.5% of overall project cost, while module cost accounts for around 50% of project cost.
    Show source
    But typically, the sensitivity is like in terms of module cost itself is around 50% of the project cost, and out of that 25%, so around 12.5% of the overall project cost is cell.
  • Cell price increases in India will have a tangible impact on CAPEX, but the tariff impact will depend on market dynamics; the percentage impact for FDRE will be lower than for pure solar tenders because solar CAPEX is only part of FDRE, which also includes wind and battery.
    Show source
    But like I said in the FDRE, the percentage will be lower as compared to pure solar tender because the solar CAPEX is just a part of the FDRE and it has wind and battery also.
  • The company said there will be enough capacity available at lower cost in India, especially on the supply chain side, which it believes will help with the IRA concern.
    Show source
    On the IRA side, which I mentioned it, this was a concern at various levels you raised to me and I believe that something will help on this because there will be enough capacity available at lower cost in India especially on the supply chain side.

Rules and policy

  • Plants were commissioned before the order on infirm power became effective from December 22nd, and its renewable merchant plants are not at risk because they can run without fuel.
    Show source
    So, all of our plants got commissioned before this order became effective.
  • The company expects an ALCM-related adjustment to reset tariffs on the solar side, with a percentage-wise smaller adjustment in an FDRE tender than in a pure solar tender; it expects the adjustment to set in by March or so.
    Show source
    So, no slowdown per s e because of any other issues, but I think the ALCM will result in a tariff reset on the solar side , it will not result in anything on the wind and battery side, but on the solar side there is a small ALCM- related adjustment which will be percentage wise far less in an FDR E tender as compared to pure solar tender.
  • Current projects are not impacted by the ALCM orders because the orders apply only to projects where bids happen after the circular, and those bids are yet to happen.
    Show source
    So, none of our projects is impacted by those orders whatever we have currently now.

What the company said on its earnings call, taken from its own transcript. Not advice.

Questions and answers

  1. Question

    My first question is with respect to the capacity that are highlighted under the LOA. Can you talk a bit about how soon can we see them getting converted and , and if you think of any capacity we could be at risk of not getting converted into ?

    Answer, nikhil dhingra

    Nikhil Dhingra: Right, right. So, if you have access to the presentation, we can go to Page #24, right, there we have given the detailed status of the tariff adoption, various steps in the overall PPA signing. So, the first thing is LOA, right? We have LOA for all of this capacity, right, which is around 4.45 GW. Now, coming to the PP A status, PPA signed for 2 ,340 MW we mentioned. I think you're more interested in what will happen to the rest of the PP A which is around 2 ,090 MW, right? So, in terms of the two projects, 380 MW of FDRE with SECI and 350 MW FDRE with SECI again, half of the PP As have been signed.

    Answer, nikhil dhingra

    So, these are expected to be signed shortly in terms of the first, they'll be first to be signed, because they have been partially sold, so they are more likely to be sold. And of course the order has been reserved for a tariff also because now that is something we also track. And in terms of the other ones, so we are quite positive that the NTPC once again will be signed shortly. So, of course we don't have because this is up to the agency to do it quickly, but what we understand in the last quarter or so, the PPA signing has really picked up pace because lot of FDRE tariffs have been adopted and lot of states have already done, like UP has done 1,200 MW for our NHPC bid which we signed yesterday, 680 MW of PPA we signed yesterday. We don't have the SECI to state government status because that is up to SECI to do it. But we understand is the top two ones will be signed very quickly, the rest of them are also very advanced, but of course and we are hopeful that they will be done in max couple of months. But this of course we keep on tracking with the counterparty.

    Answer, nikhil dhingra

    We are not able to track with the state governments, but of course we are updated that the central government is quite , quite positive about getting these power off takes done because as you know, ALCM has also come into being, so the tariffs are expected to go up as we move forward. So, these become quite attractive if you purely look at commercial angle in terms of these tariffs. Plus, as I said, the tariffs have been adopted in the recent past . So, there is a good metric for all of them. And the tariffs are in the range of what we have done in the last two years. So, we are quite hopeful that they will be signed soon. In terms of the tariff adoption, we have given detailed status wherever the order has been reserved.

    Answer, nikhil dhingra

    So , order reserved means the order will be out in next couple of months because that is the time cycle C ERC takes and we will be updating these petitions and order reserve for tariff adoption also in our quarterly presentation . In terms of the grid connectivity, we have the grid connectivity for all of them. So, if you look at our preparedness, so grid connectivity is there with us, we are of course moving forward on the land and transmission line because that's a very low CAPEX item. But of course it takes long time. So, we keep our preparedness such that we get a head start whenever the PPA get signed. 5 Stated as 4.7 GW during the call, however 4.4 GW is correct ACME Solar Holdings Limited January 29, 2025 Puneet Gulati: Just a bit of clarification on the solar one 300 MW where you talk about order reserved.

  2. Question

    This presumably it is yet to see PPA done, right, and order is the CERC order you're talking about or the PPA?

    Answer, nikhil dhingra

    Nikhil Dhingra: So, so all of 2,090 is yet to see PPA. So, 2,340 has seen the PPA right? The 2,090 is yet to see the PPA. There are two tables, right, in this slide. So, the 2,340 has seen the PPA MW, 2090, the whole of it has to see the PPA. Puneet Gulati: Understood. So, okay, second question is there was this CERC regulation which talked about not providing power charges for infirm power.

    Answer, nikhil dhingra

    Nikhil Dhingra: No, actually, we read that article, and we were going to release a clarification, our regulatory head has drafted it also, he is going to shortly do it. So, see, in terms of renewables, right, we don't have any fuel charges and other things. So, we have no, no issues with that in terms of the merchant plant or in terms of the, you can say the infirm power sale. We were of course impacted by it in the last quarter because we had to commission the plant to sell the power because this order became effective from December 22nd. So, all of our plants got commissioned before this order became effective. And of course, in renewable, the merchant plant is also not at risk because we can run our plant without fuel. But because they don't get a pass-through, the thermal projects, so they have an issue which we don't have.

  3. Question

    Puneet Gulati: And also on the other income side, if you can break it up between how much is the interest related part to it and how much is any other surcharge in somet ime?

    Answer, nikhil dhingra

    Nikhil Dhingra: Sure. So, in this quarter on the standalone basis, we paid 6 crores of taxes in this quarter. And on the consol, on the power sale, there's no tax. Arun will confirm.

    Answer, arun chopra

    Arun Chopra: So, on the other income side, so interest on FD are -- is close to around 30-odd crores. Fixed deposit.

  4. Question

    Puneet Gulati: Okay. And balance of the 28, yes.

    Answer, arun chopra

    Arun Chopra: Another 28 majorly include amortization of the deferred revenue of around INR 15 crores.

  5. Question

    Ankit Mittal: Yes, thank you for the opportunity. A few questions. So, firstly, on the cost part, cost seem to be fairly under control both on the employee and other expense front and I think this is despite us taking over employees from Cleantech. So, if you could just highlight on what's happening over there and how do you look at these costs going forward?

    Answer, manoj upadhyay

    Manoj K Upadhyay: Right, right. So, see, in terms of the cost, we have of course increased it from the last quarter because of the transfer of employees from the ACME Cleantech to ACME Solar Holdings, like we had mentioned in our DRHP. So, it has increased because of that. But in terms of the revenue and the EBITDA, because we have operational leverage, so that is where the margins are higher because the HO cost doesn't increase because of capacity expansion. So, going forward, we don't see the HO cost going up, but of course as we do more projects, right… and that will be part of the project cost of that project, we will hire a lot of people on the project side, but that will be part of that project.

    Answer, nikhil dhingra

    Nikhil Dhingra: So, actually to clarify it, it is basically as you add more and more megawatt, per megawatt cost at the corporate level will go down. ACME Solar Holdings Limited January 29, 2025 Management: So, basically, if you see these standalone financials, the costs have gone up, right, because there we are doing the EPC and all, but if you see our consolidated financials, the cost being majorly because of the project related people, it gets capitalized and gets knocked off in the capitalization front. So, you don't see a much steep hike in the consolidated financial whereas you see that in the standalone . Nikhil Dhingra : Ankit, you can refer to the slide 26 of the presentation. So, on the standalone basis, our employee benefits have moved up from INR 24 to INR 36 crores and on a, on a consol basis, they are reasonably constant.

    Answer, manoj upadhyay

    Manoj K Upadhyay: We've also taken consideration of RSU, because we have also factored the RSU will be issued through the senior management, that is also actually a method in the standalone, that's around INR 12 crores, right.

  6. Question

    Ankit Mittal: Got that. Got that. Fair. And one last question in terms of near -term commissioning, I think we have some 450 MW lined up, 150 MW of wind and 300 MW of solar merchant. When do you expect those capacities to commission?

    Answer, nikhil dhingra

    Nikhil Dhingra: So, we – yes, yes, we are doing our best to commission the 350 MW in this quarter. So, that is the intent that 350 MW gets fully commissioned. Of course, we will do our best to try and do that. It may spill over to April, 350 MW in worst case, but that is what we are trying. And the 100 MW wind, again, we'll try in best case to do it by let's say between June to September quarter. So, that's of course our intent. And in terms of the other capacities also , we have not mentioned it in advance d stages, but we have do ne most of the activit ies relating to land and transmission line.

    Answer, nikhil dhingra

    Basically, we will only say that whenever we say advanced stages, it is basically when the CAPEX has crossed 50%. So, that is what we mean by advanced stages of construction. In some cases, it is 70% CAPEX has been crossed. So, we will try and evolve some metric where we say advanced and, and where the stages of the construction of project are. But, as of now these are the projects which are in advanced stages of construction. Just on this merchant plant, I would like to say that we have won a bid at -- from SECI at INR 3.056, which we of course like we had earlier also mentioned we plan to move this merchant to any of our PPAs. So, this could be one of those PPAs where we transfer this merchant to SECI and that PPA requires you to supply power in -- before June '25.

  7. Question

    So, that's, that's great. Secondly, given that there was a lot of noise around the fact that some of the older projects… I am talking about on an all-India basis not ACME in specific, but some of the older let's say tenders which had gone out were lacking PSA and PPA signing, do you see any sluggishness or any let's say slowdown in terms of newer tendering because the government may want the older projects to see PPA, PSA signing, any of that sort happened?

    Answer, nikhil dhingra

    Nikhil Dhingra: So, in terms of the, in terms of the newer bids, right, that's what you're talking about, so we don't see a slowdown, but of course there is a temporary, temporary sort of movement into ALCM regime, right, because that is a big change which has happened where the cells need to be domestically procured. So, that will result in a shift in tariff so that we have to see where the tariff stabilizes in that regime. But of course, in terms of the bidding this year we see all the four REIAs stepping up and trying to achieve the 50 GW targets which the government has given . So, no slowdown per s e because of any other issues, but I think the ALCM will result in a tariff reset on the solar side , it will not result in anything on the wind and battery side, but on the solar side there is a small ALCM- related adjustment which will be percentage wise far less in an FDR E tender as compared to pure solar tender. So, we believe that it will definitely set in next by March or so. And this is the quarter generally where the bidding happens maximum because the targets are generally monitored very well in the l ast quarter.

  8. Question

    Subhadip Mitra: Understood. Last question is with regard to the newer capacities that you've been winning since the IPO, right? So, we used to talk about, I think 5.5 to 6 GW number earlier, now that number is already closer to 7 GW and you're planning to move towards a target at 10 GW by 2030. So, for the incremental new capacity that are being won after the fund raise, how do you see the equity funding of those projects will it be completely through internal accruals itself, will there be any requirement for further equity funding, if you can just give some color on that?

    Answer, nikhil dhingra

    Nikhil Dhingra: Sure, sure, sure, Subhadip. So, in terms of the planning of these projects, how we have planned it is that we will finish them by 2028 and that's the calendar, because we have factored in a phase signing and a phase tariff adoption, right. And, and because of that, what we are seeing is that we will commission some projects possibly in '26, some projects in '27. So, as soon as we commission, we - - our ability to securitize increases, right, our ability to get cash flow increases, right, and our ability to get EPC margin increases. So, as much commissioning we do, we generate very significant growth in accruals. So, as, as we commission something, our ability to do all these things improves. So, because of this phase wise commissioning, we don't see that we will have an equity gap in terms of ACME Solar Holdings Limited January 29, 2025 this capacity which we have won.

    Answer, nikhil dhingra

    Nikhil Dhingra: Basically, top up. Like we have mentioned in our presentation, we have raised INR 650 crores of securitization in these nine months, which you can see that we have refinanced on Slide #6, INR 5,500 crores of refinancing which have yielded INR 650 crores of top up. So, you can say that whatever debt we have, so around 13% of it, we are able to get more debt. So, that is what we mean by securitization. This is not sale of assets, just to clarify.

  9. Question

    Tejas Fulbardua: Hi. First of all, congratulations on very good results and I believe the 1,200 MW commissioning that you did this quarter that was a good achievement as well. I have three questions. Firstly, I wanted to know do you have any exposure or any sale in the US given that the noise around IRA reforms, green renewable energy by the new government in the US. I believe no, but just wanted to confirm.

    Answer, nikhil dhingra

    Nikhil Dhingra: Right. So, we don't have any sales to US because we are a utility. And in terms of the sale, all of our sale is in 25-year PPA to the utilities in India. So, all of our revenues is in rupees.

  10. Question

    That's great. The second question, I wanted to understand is, you gave an indication that you will see an annual EBITDA of INR 1,750 to INR 1,800 crores from the 2.5 GW that's online. And in one of the questions you responded that you expect around 350 MW going online in Q4 this year or maybe April '25. So, should I expect maybe around 10 %, 15% additional revenue from that like INR 200 crores or higher revenue from that annually next year?

    Answer, nikhil dhingra

    Nikhil Dhingra: Yes, you can expect that because like we said, I can tell you more about those projects. So, of the 350 MW project, 50 MW is at a tariff of INR 2.907. It's a wind project. Wind projects typically have a CUF higher than 30%. So, you can do the maths in terms of the revenue. And in terms of the merchant tariff, in the past quarter or so, we have sold power in the range of INR 2.7 to INR 3 sometimes. So, that's the tariff you can assume on an average basis more than INR 3 we have for the merchant plan of 300 MW.

    Answer, nikhil dhingra

    Of course, like I said, we have got a PP A of 3.05 for that. So, if the PPA gets signed before June, so the 3.05 is the revenue on the 300 MW and otherwise closer to 3 only. So, this will definitely be more than 10%, ye s. Manoj K Upadhyay: And this will be also operating at 30% CUF, because these plants are designed with 150% of overloading.

Show 9 more questions
  1. Question

    Tejas Fulbardua: Great. Thanks for all the clarification.

    Answer, nikhil dhingra

    Nikhil Dhingra: No, no, , it is not full potential. It is of course this project can do an annual EBITDA of around INR 720-odd crores if you take 30% CUF. So, it can do at its best around INR 180 crores but it is seasonal, right?

    Answer, nikhil dhingra

    Nikhil Dhingra: Yes, yes. Gopal: How much have you spent? Management: So, in nine months, we have done roughly INR 3,500 crores of CAPEX for this particular year. Gopal: Okay. And what is the target for this year?

    Answer, nikhil dhingra

    Nikhil Dhingra: So, this year, like we said, this 350 MW, we need to commission. So, Arun, any idea on what's the CAPEX left? I think less than that, it should be less than that, around INR 800 crores of CAPEX we will be doing in the next six months in next two quarters. Gopal: And Financial Year ‘2 6, what is the CAPEX target?

    Answer, nikhil dhingra

    Nikhil Dhingra: It is INR 4,600 crores. If you, if you look at the, I think the actual CAPEX, so INR 4,600 crores. Gopal: Okay.

    Answer, nikhil dhingra

    Nikhil Dhingra: It is no impact because if you read the ALCM circular, it is applicable only for the projects where the bids happen post that circular. So, actually those bids are yet to happen. They will start happening now as we speak. So, none of our projects is impacted by those orders whatever we have currently now. We don't have any impact, no pass-through also because we will not be even required to follow that order for these projects. ACME Solar Holdings Limited January 29, 2025 Gopal: Okay. And in your opinion, with the current cell prices in India, what should be the increase in the tariff for pure solar?

    Answer, nikhil dhingra

    Nikhil Dhingra: So, that's something which we need to see, because it's a very dynamic market because ultimately you are dependent on China for the value chain. So, we will not be able to comment on that, but it will result in some I think definitely a tangible increase. But like I said in the FDRE, the percentage will be lower as compared to pure solar tender because the solar CAPEX is just a part of the FDRE and it has wind and battery also. But it will be an impact. But of course, the market will decide that impact because how much of the industry absorbs that and how much it passes it on is a function of the market dynamics. So, in terms of the tariffs, we cannot say, but in terms of the CAPEX, cell prices I can give you some idea that - Gopal: Yes, that will help.

    Answer, nikhil dhingra

    Nikhil Dhingra: Yes. So, let's say without these ALCM, typically cell constitutes currently around 25% of the overall module price if you look at the cell. You can do your sensitivities. I don't know the amount of the increase the cell prices will have in India, because that's something markets still have to clear, because the lot of capacities are coming up in India. But typically, the sensitivity is like in terms of module cost itself is around 50% of the project cost, and out of that 25%, so around 12.5% of the overall project cost is cell. So, whatever increases there, that will be the sensitivity you can do. Gopal: Okay.

  2. Question

    Akash Mehta: Hi, sir, congratulation on good set of numbers. So, my first question is, sir, you mentioned in terms of the grid connectivity, that gr id connectivity for under-construction capacity is in place. So, in terms of land, so how would you kind of look at it , also most of the land in place for forward capacity we have?

    Answer, nikhil dhingra

    Nikhil Dhingra: Right, right. So, the land we of course keep on acquiring land for each of the projects. But in terms of our prioritization for the signed PPA one s we prioritize them in P1. So, we will give you update on the solar side and wind side both , so we are close to around 5,000-odd acres land for the under- construction projects and for the wind location around 104 locations we have the land for these projects.

    Answer, manoj upadhyay

    Manoj K Upadhyay: 400 to 500 MW. Nikhil Dhingra: So, so and this number is, is very dynamic. It keeps on updating every quarter. We have chosen not to update it because it's very, very dynamic. And in terms of the timelines, this is -- we are acquiring land even for projects which are far ahead sometimes and, and of course our aim is, like we said, in terms of prioritization, our aim is that for the PPA signed projects, the land should be in place ideally within six months of the PPA signing, completely done and in, in worst case, around 9 to 12 months.

  3. Question

    Akash Mehta: Okay. I think that's helpful. And second is I just wanted to clarify on this merchant capacity. So, that will be 300 MW and that 350 MW you mentioned that would be separate, right? That's solar. Two projects are separate or - ACME Solar Holdings Limited January 29, 2025 Nikhil Dhingra: Yes.

    Answer, nikhil dhingra

    The merchant capacity is only 300 MW. We don't have any more merchant capacity and that merchant capacity also; our intent is not to have merchant for 25-years. It will be merchant till the time we find a good resting place for it in terms of a PPA. And we have found that with the SECI tender of INR 3.05 which we have won. So, that is the only merchant we have in the portfolio.

  4. Question

    Akash Mehta: Sir, how are you looking at merchant tariffs, moving on like from last maybe a quarter or so, are they improving or still, there's more supply in the market ?

    Answer, manoj upadhyay

    Manoj K Upadhyay: I think quarterly if you see that quarter-by-quarter, it has improved, but our fundamental is that we don't want to have a merchant actually. Three, four, five months, that's what our plan is to run it and after that find a PPA which Nikhil was explaining. And we have already found a PPA where we will fix -- we will transfer this project, right, at INR 3.058 tariff for 25-years.

  5. Question

    Nikhil Abhyankar: Okay. And sir, we have refinanced our operational projects at 8.8%. Is there any scope of further reduction in these rates because there are some players who are doing it at lower level as well?

    Answer, nikhil dhingra

    Nikhil Dhingra: Yes, yes. So, we have mentioned to you the average rate. Even we are able to get rates of 8.6, 8.5 also for some of our projects. See, sometimes what happens is, it is a tradeoff between taking securitization proceeds and the rate because you have to take a call , definitely lower rates are possible just to answer your question, definitely lower rates are possible , because the rating of these projects, already we have managed to get AA- for our refinancing. So, the rating upgrade is a company-specific upside which will help us in getting lower rates because we have just done the IPO, we have just paid the debt on the corporate level basically on the consolidated level. So, we will basically get the upside of that in the upcoming quarters . And of course, the rates from a company-specific reason, one is the rating upgrade because of the overall equity raise.

    Answer, nikhil dhingra

    And secondly, because of the rating upgrade, because of the counterparties AAA for us in all of our PPAs, which we are executing. So, as we said on the operational side also, around 70% is AAA. So, that is the upside possible on the company- specific reasons. Of course, that's again a macro call whether the rates will be cut or not. Because what we are trying to do is borrow more on the variable rates and which will help us come down as the MCLR comes down. So, that's a macro call, which I think you guys know better on that, but on the company-specific reason there is definitely room to improve on these rates. And some of these loans we are taking have a rating-related rate reduction also.

    Answer, nikhil dhingra

    Let's say in some products we got a Single A rating. But if we manage to go to AA, the rate will fall by let's say 25 to 30 basis points. Because the rating upgrades, the rates can come down depending on each specific product.

  6. Question

    Nikhil Abhyankar: Thank you. And sir, now harping back on our equity requirement over the next three, four years, the back of the paper calculation shows our CAPEX of around INR 45,000 crores in the next three years to complete the entire 4.6 GW of pipeline. This will entail equity requirement of almost INR 7,500- INR 8,000 crores. So, how do we exactly plan on achieving that? ACME Solar Holdings Limited January 29, 2025 Nikhil Dhingra: Right.

    Answer, nikhil dhingra

    So, it is, I think, three sources of equity for us like we said. So, we have raised INR 2,400 crores of IPO money, right. So, that is the most significant part of that INR 7,500 crores requirement, then of course securitization proceeds are the second most important part of that component, out of which we have already managed to raise around INR 650-odd crores like we mentioned in these nine months. And of course, the SECI project we just updated you, will add at least INR 1,000-odd crores in terms of securitization proceeds. So, you can say securitization will add around INR 2,500-odd crores on top of the INR 2,400 crores we have from the IPO. And the third source of this is the construction margins. Like we guided you on the 5% to 7% EPC margins.

    Answer, nikhil dhingra

    On whatever we construct from this INR 45,000 crores, so you can expect EPC accruals of around INR 2,000 to INR 2,500 crores. So, these are the three sources. On top of that, there is free cash flow from running projects. So, that will also give us buffer to have more cash flows than required.

  7. Question

    Jainam Jain: Sir. So, when do we expect the conclusion of PPA signing for 190 MW plus 150 MW FDRE requisites?

    Answer, nikhil dhingra

    Nikhil Dhingra: Yes, so that's the question we also keep following on with SECI. So, ultimately, the PPA signing is done by SECI. So, what we understand is that they are in discussion with a few state governments, principally some of the states which they have already signed up with, like SECI has signed up with Chhattisgarh for 190 MW. So, that is the one party which they are talking to for the rest of the capacity… and of course they're talking to Uttar Pradesh, Madhya Pradesh for this. But that is up to them. So, we don't have a day-by-day status for the PPA signing. But what we understand is they should be signed soon because half of the capacity is already signed.

  8. Question

    Okay. And sir, do you start the work or commit capital before the order is reserved by the CERC or signing off PPA?

    Answer, nikhil dhingra

    Nikhil Dhingra: We take the connectivity because the connectivity is applied on the basis of the letter of award. So, connectivity we take, there is no cost attached to it other than the very small, bank guarantees you need to give, then we start acquiring land, because land is something you can use for any project, right, so land is a useful resource, and it is an appreciating resource. So, we start buying land at the place where we take connectivity, but that is less than 1% of the CAPEX. But of course, and this CAPEX is reusable, this is not something which is sunk if there is any issue on that option and all things. So, we don't do CAPEX, which is non-recoverable before the tariff is adopted.

  9. Question

    Jainam Jain: Alright sir. That answers my question. Thank you and all the best.

    Answer, manoj upadhyay

    Manoj K Upadhyay: My name is Manoj Upadhyay. I would like to thank you all for patiently hearing and asking the right questions. This quarter has been a very, very important thing for us because this 1 ,200 MW, one of the biggest projects we were making and it was important for us to achieve it. We also wanted to show performance improvement especially in the PAT side as well as on our CUF side. I think our team has done exceptionally well on that. We are also able to create a pipeline not up to '26, but beyond '26 also. And our focus will remain that any future pipeline or whatever we create, we create towards '28 to '30 timelines, so we achieve a 10 GW, our target.

    Answer, manoj upadhyay

    ACME Solar Holdings Limited January 29, 2025 We are still building more resources on the team side; so a very senior person who joined us as a president of our execution on projects, he came from the very well -established ABB background where he was the M.D. of the ABB Execution India and that company became Linxon. On the quality side also, we are improving because we will do so many projects and we have added many, many project directors. So, they ensure that we are in cost and quality we are managing that. And ACME is known for its innovation and this thing. So, we want to also do that, put the new technology in test and I think in this quarter or next three, four months, we will set up one small FDRE project because I have seen in many interaction that people had some concern on FDRE, although, yes, FDRE is not this thing because we have been forecasting our power under deviation settlement mechanism for last four, five years. So, technically it is the same deviation settlement mechanism and forecasting with the battery inside which will improve it further. On the IRA side, which I mentioned it, this was a concern at various levels you raised to me and I believe that something will help on this because there will be enough capacity available at lower cost in India especially on the supply chain side.

Questions about this call

When was the Acme Solar Holdings Q3 FY25 earnings call transcript filed?
Acme Solar Holdings filed the transcript with the exchange on 3 Feb 2025. This page is built from that transcript.
What does this page list?
94 statements from the transcript across 10 topics, 73 of them with a figure. Each statement is shown with the transcript sentence it came from.
Are the analysts' questions included?
Yes. 19 questions and management's answers are listed in the order they were asked, as the transcript prints them.
Who wrote this page?
DalalOS Data Desk. Assembled by software from the company's transcript. Not reviewed by a person. How it is made, and what it leaves out, is on the method page linked from the byline.
Research and analysis only, not investment advice. Every statement on this page is the company's own, taken from its transcript; DalalOS adds no view on it and is not a SEBI-registered investment adviser. Something wrong? Report an error.